12972-12974 W VAUGHN ST 91340
Certificate Information: 12972-12974 W VAUGHN ST 91340
- Application / Permit
- 25016-20000-02846
- Plan Check / Job No.
- B25VN02511
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: Attached Garage conversion to ADU per GCS 66323(a)(1). Work per WFPP.
- Permit Issued
- Issued on 2/24/2025
- Issuing Office
- Current Status
- CofO Issued on 12/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2025 | MINA HABILI |
| Corrections Issued | 2/10/2025 | MINA HABILI |
| Plan Check Approved | 2/13/2025 | TSE MING HUANG |
| Issued | 2/24/2025 | APPLICANT |
| CofO in Progress | 11/21/2025 | MICHEL ABAJAN |
| Permit Finaled | 12/3/2025 | RUBEN SALAS |
| CofO Issued | 12/3/2025 | RUBEN SALAS |
| Permit Finaled | 12/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 2/10/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 4/11/2025 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/17/2025 | Approved | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 4/18/2025 | Conditional Approval | RAUL OLAGI |
| Sewer | 4/21/2025 | Approved | MICHEL ABAJAN |
| Special/Order Compliance | 4/21/2025 | Partial Inspection | RAUL OLAGI |
| Pre-Inspection | 4/30/2025 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/14/2025 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/16/2025 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/18/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/18/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 7/23/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/25/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/25/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 7/25/2025 | Approved | MICHEL ABAJAN |
| Insulation | 7/29/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 7/29/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 8/1/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 10/14/2025 | Approved | MICHEL ABAJAN |
| Final | 10/14/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 10/14/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 10/14/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 10/14/2025 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 10/14/2025 | Approved | MICHEL ABAJAN |
| Final | 11/18/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 11/20/2025 | OK to Issue CofO | MICHEL ABAJAN |