1020 1/4 E 33RD ST 90011

Certificate Information: 1020 1/4 E 33RD ST 90011

Application / Permit
25016-20000-02416
Plan Check / Job No.
B25VN02074
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) ATTACHED 4-CAR GARAGE INTO NEW ADU (780.0 SF). PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/5/2025
Issuing Office
Current Status
CofO Issued on 3/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2025 APPLICANT
Assigned to Plan Check Engineer 1/31/2025 ALFREDO JARA
Corrections Issued 2/2/2025 ALFREDO JARA
Plan Check Approved 3/3/2025 ALFREDO JARA
Issued 3/5/2025 APPLICANT
CofO in Progress 2/24/2026 ALEJANDRO DE ARTOLA
No Progress 2/25/2026 MICHAEL LEWIS
CofO in Progress 2/25/2026 MICHAEL LEWIS
Permit Finaled 3/13/2026 DEROLD HAUFF
Permit Finaled 3/13/2026 DEROLD HAUFF
CofO Issued 3/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/7/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 2/7/2025 TAL SHEMEN
Sewer availability Cleared 2/7/2025 TAL SHEMEN
ZI Cleared 2/12/2025 YINGSHI HUANG

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/24/2025 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 7/16/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 7/16/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/5/2025 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/6/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 8/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/6/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 8/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/13/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 8/13/2025 Approved ALEJANDRO DE ARTOLA
Insulation 8/13/2025 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 8/13/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 8/28/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 9/17/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 11/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 11/14/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 11/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 11/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Verify Rec and Parks Fee Memo 11/14/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 11/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 11/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 11/25/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 11/26/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 11/26/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/24/2026 Approved ALEJANDRO DE ARTOLA
Final 2/24/2026 OK to Issue CofO ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 2/24/2026 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 2/24/2026 Approved ALEJANDRO DE ARTOLA