11746 W BLIX ST 91607

Certificate Information: 11746 W BLIX ST 91607

Application / Permit
25016-20000-02405
Plan Check / Job No.
B25VN02065
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE ALL THE EXTERIOR AND INTERIOR WALLS OF AN EXISTING SFD EXCEPT 5.58 LF OF WALL AND FOUNDATION AT SOUTH PORTION OF THE LOT AND BUILD 29' X 29'1" CONVERT SFD TO ACCESORY DWELLING UNIT AS PER GC 66323(a)(1) WITH 14'2" X 13'5" OPEN TRELLIS , ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/5/2025
Issuing Office
Current Status
CofO Issued on 4/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 RARES BODEA
Corrections Issued 2/3/2025 RARES BODEA
Quality Review Completed 2/3/2025 STEVEN KIM
Building Plans Picked Up 2/5/2025 APPLICANT
Plan Check Approved 3/5/2025 RARES BODEA
Issued 3/5/2025 APPLICANT
CofO in Progress 12/22/2025 JAVIER RAMOS JR
CofO in Progress 3/28/2026 RAUL OLAGI
CofO Issued 4/15/2026 RUBEN SALAS
Permit Finaled 4/15/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/3/2025 CARLOS AGUILERA
Sewer availability Cleared 2/3/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/4/2025 CARLOS AGUILERA
Miscellaneous Cleared 2/5/2025 JOANNA MARROQUIN
Specific Plan Cleared 2/5/2025 JOANNA MARROQUIN
ZI Cleared 2/5/2025 JOANNA MARROQUIN
ZI Cleared 2/5/2025 JOANNA MARROQUIN
Low Impact Development (LID) Cleared 2/11/2025 SARAH YOUSSEF
Construction near power lines Cleared 2/25/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/8/2025 Approved KEVIN BERBERYAN
Underground Mechanical 4/8/2025 Approved KEVIN BERBERYAN
Deputy Drilled-In Anchors 4/11/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/15/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 4/15/2025 Partial Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 4/30/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/5/2025 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/5/2025 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 6/5/2025 Approved JAVIER RAMOS JR
Underground Mechanical 6/5/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 6/10/2025 Partial Inspection JAVIER RAMOS JR
Deputy Wood Construction 6/10/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 6/10/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/10/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/13/2025 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Approved JAVIER RAMOS JR
Shower Pan 6/13/2025 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 6/13/2025 Approved JAVIER RAMOS JR
Insulation 6/25/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/25/2025 Approved JAVIER RAMOS JR
Drywall Nailing 7/1/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 12/9/2025 Corrections Issued CRAIG DAVIS
HVAC-Final 12/9/2025 Corrections Issued CRAIG DAVIS
PLUMBING-Final 12/9/2025 Corrections Issued CRAIG DAVIS
Service/Power Release 12/9/2025 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 12/19/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/19/2025 Approved JAVIER RAMOS JR
Final 12/19/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 12/19/2025 Approved JAVIER RAMOS JR
Green Building Rough 12/19/2025 Approved JAVIER RAMOS JR
HVAC-Final 12/19/2025 Approved JAVIER RAMOS JR
MERV13>=Final 12/19/2025 Approved JAVIER RAMOS JR
MERV13>=Rough 12/19/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 12/19/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 12/19/2025 Approved JAVIER RAMOS JR
Smoke Detectors 12/19/2025 Approved JAVIER RAMOS JR