9500 N EL DORADO AVE 91352

Certificate Information: 9500 N EL DORADO AVE 91352

Application / Permit
25016-20000-02385
Plan Check / Job No.
B25VN02044
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
EPLAN: TENANT IMPROVEMENT TO (E) OFFICE AND INSTALL ROOFTOP EQUIPEMENT
Permit Issued
Issued on 4/8/2025
Issuing Office
Current Status
Permit Finaled on 4/9/2026

Permit Application Status History

Submitted 1/29/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 RAPHAEL ROSAS
Assigned to Zoning Architect 1/30/2025 MEGAN KOLP
Corrections Issued 2/3/2025 RAPHAEL ROSAS
Quality Review Completed 2/4/2025 STEVEN KIM
Applicant returned to address corrections 3/19/2025 RAPHAEL ROSAS
Plan Check Approved 3/27/2025 RAPHAEL ROSAS
Issued 4/8/2025 APPLICANT
Permit Finaled 4/9/2026 ANDREW DORSO

Permit Application Clearance Information

Green Code Cleared 2/12/2025 MICHAEL AYERS
Sewer availability Cleared 2/12/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/19/2025 RYAN CASTRO
Metro Rail approval Cleared 2/25/2025 JENNIFER SU
DAS Clearance Cleared 3/13/2025 Gurunath Nesarajah
Zoning Plan Check Cleared 3/21/2025 MEGAN KOLP

Contact Information

Architect Dwyer,, Mark Steven; Lic. No.: C23283 PO BOX 1392      WRIGHTWOOD, CA 92397
Contractor Norm Wilson & Sons Inc; Lic. No.: 435700-B       ,

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 5/20/2025 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 6/4/2025 Conditional Approval ANDREW DORSO
Excavation/Setback/Form/Re-Bar 6/9/2025 Partial Approval BRIAN KELLY
Deputy Drilled-In Anchors 6/13/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 6/13/2025 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 6/16/2025 Conditional Approval BRIAN KELLY
Drywall Nailing 6/16/2025 Not Ready for Inspection BRIAN KELLY
Excavation/Setback/Form/Re-Bar 6/16/2025 Partial Approval BRIAN KELLY
Special/Order Compliance 6/23/2025 Partial Inspection BRIAN KELLY
Drywall Nailing 6/24/2025 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 6/25/2025 Conditional Approval ANDREW DORSO
Special/Order Compliance 6/30/2025 Partial Inspection ANDREW DORSO
Insulation 7/15/2025 Partial Inspection ANDREW DORSO
Interior/Exterior Lathing 7/15/2025 Approved ANDREW DORSO
Excavation/Setback/Form/Re-Bar 7/25/2025 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 7/25/2025 Partial Inspection ANDREW DORSO
Drywall Nailing 7/30/2025 Partial Inspection ANDREW DORSO
Final 7/30/2025 Corrections Issued ANDREW DORSO
Insulation 7/30/2025 Approved ANDREW DORSO
Drywall Nailing 8/5/2025 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 8/15/2025 Conditional Approval ANDREW DORSO
Light Gage Steel Frame 8/20/2025 Approved ANDREW DORSO
Drywall Nailing 8/27/2025 Partial Approval RAFAEL CORTES
T-Bar Ceiling 9/19/2025 Corrections Issued ANDREW DORSO
Drywall Nailing 10/8/2025 Approved ANDREW DORSO
T-Bar Ceiling 10/22/2025 Approved ANDREW DORSO
Footing/Foundation/Slab 11/26/2025 Approved KENNETH ROBERTS
Deputy Drilled-In Anchors 12/15/2025 Conditional Approval ANDREW DORSO
Final 4/3/2026 Not Ready for Inspection ANDREW DORSO
Green Building Final 4/3/2026 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 4/3/2026 SGSOV Approved ANDREW DORSO
Smoke Detectors 4/3/2026 Approved ANDREW DORSO
Final 4/9/2026 Permit Finaled ANDREW DORSO