6410 W 86TH PL 90045

Certificate Information: 6410 W 86TH PL 90045

Application / Permit
25016-20000-02366
Plan Check / Job No.
B25VN02024
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(b)(1).
Permit Issued
Issued on 6/9/2025
Issuing Office
Valley
Current Status
CofO Issued on 1/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2025 APPLICANT
Assigned to Plan Check Engineer 2/5/2025 HAYATO TSUCHIYA
Corrections Issued 2/6/2025 HAYATO TSUCHIYA
Building Plans Picked Up 2/7/2025 APPLICANT
Applicant returned to address corrections 5/23/2025 HAYATO TSUCHIYA
Plan Check Approved 6/6/2025 NAREG ATARIAN
Issued 6/9/2025 APPLICANT
CofO in Progress 1/22/2026 JESUS PINEDA
Permit Finaled 1/22/2026 RICHARD STEINBACH
CofO Issued 1/22/2026 RICHARD STEINBACH
Permit Finaled 1/22/2026 RICHARD STEINBACH

Permit Application Clearance Information

Construction within easement Cleared 4/2/2025 RIDWAN HARDY
Address approval Cleared 4/4/2025 LIAM ODONOVAN
Sewer availability Cleared 4/4/2025 LIAM ODONOVAN
Specific Plan Cleared 4/4/2025 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 4/22/2025 LIAM ODONOVAN

Contact Information

Contractor Owner-Builder       ,
Engineer Shectman,, Leonid; Lic. No.: C47840 5222-3 LINDLEY AVE      ENCINO, CA 91316

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/16/2025 Partial Inspection TEMISTOCLES CAAL
PLUMBING-Rough 7/29/2025 Partial Approval JESUS PINEDA
Sewer 7/29/2025 Approved JESUS PINEDA
Footing/Foundation/Slab 8/26/2025 Approved JESUS PINEDA
Underground Mechanical 8/26/2025 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 9/23/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 9/23/2025 Corrections Issued JESUS PINEDA
Green Building Rough 9/23/2025 Corrections Issued JESUS PINEDA
Wood Frame 9/23/2025 Not Ready for Inspection JESUS PINEDA
BUILDING-Rough-Frame 10/7/2025 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 10/7/2025 Not Ready for Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Corrections Issued JESUS PINEDA
Green Building Rough 10/7/2025 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 10/7/2025 Not Ready for Inspection JESUS PINEDA
BUILDING-Rough-Frame 10/9/2025 Partial Approval JESUS PINEDA
ELECTRICAL-Rough 10/9/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Approved JESUS PINEDA
Green Building Rough 10/9/2025 Approved JESUS PINEDA
HVAC-Rough 10/9/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 10/9/2025 Approved JESUS PINEDA
HVAC-Rough 10/15/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 10/20/2025 Approved JESUS PINEDA
Insulation 10/20/2025 Corrections Issued JESUS PINEDA
Drywall Nailing 10/30/2025 Approved JESUS PINEDA
Insulation 10/30/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 11/12/2025 Approved JESUS PINEDA
Service/Power Release 11/12/2025 Not Ready for Inspection JESUS PINEDA
Shower Pan 11/12/2025 Approved JESUS PINEDA
ELECTRICAL-Final 12/10/2025 Corrections Issued JESUS PINEDA
Final 12/10/2025 Corrections Issued JESUS PINEDA
Green Building Final 12/10/2025 Corrections Issued JESUS PINEDA
HVAC-Final 12/10/2025 Approved JESUS PINEDA
PLUMBING-Final 12/10/2025 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 12/10/2025 SGSOV Not Required JESUS PINEDA
Smoke Detectors 12/10/2025 Approved JESUS PINEDA
ELECTRICAL-Final 1/21/2026 Approved JESUS PINEDA
Final 1/21/2026 OK to Issue CofO JESUS PINEDA
Green Building Final 1/21/2026 Approved JESUS PINEDA
PLUMBING-Final 1/21/2026 Approved JESUS PINEDA
Service/Power Release 1/21/2026 Approved JESUS PINEDA