7450-7452 N PONCE AVE 91307

Certificate Information: 7450-7452 N PONCE AVE 91307

Application / Permit
25016-20000-02362
Plan Check / Job No.
B25VN02017
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GC 66323(a)(1)
Permit Issued
Issued on 2/14/2025
Issuing Office
Valley
Current Status
CofO Issued on 7/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2025 APPLICANT
Assigned to Plan Check Engineer 2/3/2025 JESSE ARELLANO
Corrections Issued 2/3/2025 JESSE ARELLANO
Building Plans Picked Up 2/7/2025 APPLICANT
Plan Check Approved 2/14/2025 HAYATO TSUCHIYA
Issued 2/14/2025 APPLICANT
CofO in Progress 7/11/2025 CHRIS CHRISTENSEN
CofO Issued 7/18/2025 DANIEL ORRANTE
Permit Finaled 7/18/2025 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/10/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 2/10/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/10/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/11/2025 Approved CHRIS CHRISTENSEN
Sewer 4/11/2025 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 4/16/2025 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/16/2025 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 4/28/2025 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/8/2025 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 5/8/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 5/8/2025 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/21/2025 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/21/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 5/21/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/23/2025 Partial Approval CHRIS CHRISTENSEN
Insulation 5/23/2025 Conditional Approval CHRIS CHRISTENSEN
Shower Pan 5/23/2025 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Approved CHRIS CHRISTENSEN
Insulation 5/27/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/27/2025 Approved CHRIS CHRISTENSEN
Drywall Nailing 5/29/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/29/2025 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 6/2/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/7/2025 Approved CHRIS CHRISTENSEN
Final 7/7/2025 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 7/7/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 7/7/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/7/2025 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 7/7/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 7/7/2025 Approved CHRIS CHRISTENSEN
Final 7/9/2025 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 7/9/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 7/9/2025 Approved CHRIS CHRISTENSEN