8237 N VANSCOY AVE 91605

Certificate Information: 8237 N VANSCOY AVE 91605

Application / Permit
25016-20000-02300
Plan Check / Job No.
B25VN01973
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
Permit Issued
Issued on 3/13/2025
Issuing Office
Valley
Current Status
CofO Issued on 1/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2025 APPLICANT
Assigned to Plan Check Engineer 2/3/2025 ISIS ARGUETA
Corrections Issued 2/3/2025 ISIS ARGUETA
Building Plans Picked Up 2/5/2025 APPLICANT
Plan Check Approved 3/13/2025 ALEC MOUSAKHANIAN
Issued 3/13/2025 APPLICANT
CofO in Progress 1/14/2026 MATTHEW NELSON
Permit Finaled 1/30/2026 RUBEN SALAS
CofO Issued 1/30/2026 RUBEN SALAS
Permit Finaled 1/30/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/6/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/6/2025 CARLOS AGUILERA
Sewer availability Cleared 2/6/2025 CARLOS AGUILERA
Construction near power lines Cleared 3/6/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/27/2025 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 4/22/2025 Partial Approval MICHAEL CORTEZ
BUILDING-Rough-Frame 5/1/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 5/1/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Rough 5/1/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 5/1/2025 Corrections Issued NICHOLAS TROWBRIDGE
Sewer 5/1/2025 Approved NICHOLAS TROWBRIDGE
Underground Mechanical 5/1/2025 Partial Approval NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 5/5/2025 Partial Approval NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 5/5/2025 Approved NICHOLAS TROWBRIDGE
Green Building Final 5/5/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 5/5/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 5/5/2025 Approved NICHOLAS TROWBRIDGE
Insulation 5/9/2025 Corrections Issued MICHAEL CORTEZ
Interior/Exterior Lathing 5/9/2025 Approved MICHAEL CORTEZ
Shower Pan 5/9/2025 Approved MICHAEL CORTEZ
Insulation 5/14/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 5/16/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 7/16/2025 Corrections Issued MATTHEW NELSON
Final 7/16/2025 Corrections Issued MATTHEW NELSON
Green Building Rough 7/16/2025 Approved MATTHEW NELSON
HVAC-Final 7/16/2025 Corrections Issued MATTHEW NELSON
PLUMBING-Final 7/16/2025 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Approved MATTHEW NELSON
Smoke Detectors 7/16/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 9/4/2025 Approved MATTHEW NELSON
Final 9/4/2025 Not Ready for Inspection MATTHEW NELSON
MERV13>=Final 9/4/2025 Approved MATTHEW NELSON
MERV13>=Rough 9/4/2025 Approved MATTHEW NELSON
Final 12/4/2025 Corrections Issued MATTHEW NELSON
ELECTRICAL-Final 12/8/2025 Not Ready for Inspection MATTHEW NELSON
Final 1/14/2026 OK to Issue CofO MATTHEW NELSON
Service/Power Release 1/14/2026 Approved MATTHEW NELSON