10330 N MASON AVE 91311
Certificate Information: 10330 N MASON AVE 91311
- Application / Permit
- 25016-20000-02036
- Plan Check / Job No.
- B25VN01707
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- EPLAN TENANT IMPROVEMENT TO (E) GROCERY STORE AND INSTALL NEW ROOFTOP EQUIPMENT AND ENLARGE LOADING DOCK AT REAR
- Permit Issued
- Issued on 8/13/2025
- Issuing Office
- Current Status
- Permit Finaled on 3/12/2026
Permit Application Status History
| Submitted | 2/4/2025 | APPLICANT |
| Assigned to Zoning Architect | 2/6/2025 | FRANCIS AHN |
| Assigned to Plan Check Engineer | 2/6/2025 | RAPHAEL ROSAS |
| Corrections Issued | 2/11/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 2/12/2025 | STEVEN KIM |
| Applicant returned to address corrections | 4/8/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 8/13/2025 | RAPHAEL ROSAS |
| Issued | 8/13/2025 | APPLICANT |
| Permit Finaled | 3/11/2026 | EDWIN GREGORYONA |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/12/2025 | DORIAN AGUILAR |
| Miscellaneous | Cleared | 2/12/2025 | DORIAN AGUILAR |
| Specific Plan | Cleared | 2/12/2025 | DORIAN AGUILAR |
| ZA Case | Cleared | 2/12/2025 | DORIAN AGUILAR |
| ZI | Cleared | 2/12/2025 | DORIAN AGUILAR |
| Green Code | Cleared | 5/8/2025 | MICHAEL AYERS |
| DAS Clearance | Cleared | 8/6/2025 | Rosendo Medina |
| Zoning Plan Check | Cleared | 8/7/2025 | Rosendo Medina |
Contact Information
| Architect | Sargenti,, Robert Jon; Lic. No.: C31054 | 461 FROM ROAD SUITE 255 PARAMUS, NJ 07652 |
| Contractor | B S M Construction Inc; Lic. No.: 828014-B | , |
| Engineer | Pineda,, Salvador Antonio; Lic. No.: S5233 | 560 W MAIN STREET SUITE C-328 ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/21/2025 | Corrections Issued | DEANDRE HOFFMAN |
| Wood Frame | 8/21/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Wood Frame | 8/25/2025 | Partial Approval | DEANDRE HOFFMAN |
| Wood Frame | 8/27/2025 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 9/8/2025 | Approved | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 9/8/2025 | Partial Approval | DEANDRE HOFFMAN |
| Special/Order Compliance | 9/8/2025 | Corrections Issued | DEANDRE HOFFMAN |
| Pre-Inspection | 9/10/2025 | Not Ready for Inspection | GREGORY POMISH |
| Structural Steel Frame | 9/10/2025 | Partial Inspection | GREGORY POMISH |
| Reinforced Concrete Frame | 9/11/2025 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 9/17/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 9/18/2025 | Partial Approval | DEANDRE HOFFMAN |
| Wood Frame | 11/17/2025 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 11/19/2025 | Approved | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 11/24/2025 | Not Ready for Inspection | GREGORY POMISH |
| Structural Steel Frame | 11/24/2025 | Not Ready for Inspection | GREGORY POMISH |
| T-Bar Ceiling | 11/26/2025 | Approved | DEANDRE HOFFMAN |
| Final | 2/6/2026 | Off-Hour Fees Due | |
| Green Building Final | 2/6/2026 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 2/6/2026 | Off-Hour Fees Due | |
| Smoke Detectors | 2/6/2026 | Off-Hour Fees Due | |
| Final | 3/11/2026 | Permit Finaled | EDWIN GREGORYONA |
| Green Building Final | 3/11/2026 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 3/11/2026 | Approved | EDWIN GREGORYONA |