10342-10344 N PETIT AVE 91344

Certificate Information: 10342-10344 N PETIT AVE 91344

Application / Permit
25016-20000-01939
Plan Check / Job No.
B25VN01605
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN---CONVERT EXISTING ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT per GCS 66323(a)(1). ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/26/2025
Issuing Office
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2025 APPLICANT
Assigned to Plan Check Engineer 1/27/2025 ARAMIK SHAHMIRZAIAN
Corrections Issued 1/28/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 2/20/2025 ARAMIK SHAHMIRZAIAN
Issued 3/26/2025 APPLICANT
CofO in Progress 9/24/2025 NICHOLAS TROWBRIDGE
CofO Issued 10/14/2025 RUBEN SALAS
Permit Finaled 10/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/30/2025 RYAN CASTRO
Sewer availability Cleared 1/30/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/31/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/17/2025 Partial Approval NICHOLAS TROWBRIDGE
Sewer 4/17/2025 Approved NICHOLAS TROWBRIDGE
Deputy Drilled-In Anchors 5/27/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 5/27/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 7/28/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 7/29/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 7/29/2025 Approved NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 7/29/2025 Corrections Issued NICHOLAS TROWBRIDGE
Gas Test 7/29/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 7/29/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 7/29/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/29/2025 Approved NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 7/29/2025 Approved NICHOLAS TROWBRIDGE
Sewer 7/29/2025 Approved NICHOLAS TROWBRIDGE
Wood Frame 7/29/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 7/31/2025 Partial Approval CHRISTOPHER ROJAS
Shower Pan 7/31/2025 Approved CHRISTOPHER ROJAS
Special/Order Compliance 7/31/2025 Approved CHRISTOPHER ROJAS
Insulation 8/4/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 8/7/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/7/2025 Approved MISAEL ESPARZA
PLUMBING-Rough 8/21/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/17/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 9/17/2025 Corrections Issued CHRISTOPHER ROJAS
Final 9/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 9/17/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 9/17/2025 Approved CHRISTOPHER ROJAS
HVAC-Final 9/17/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 9/17/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 9/17/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 9/17/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 9/22/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Final 9/22/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Final 9/22/2025 Approved NICHOLAS TROWBRIDGE
Final 9/23/2025 OK to Issue CofO NICHOLAS TROWBRIDGE
Green Building Final 9/23/2025 Approved NICHOLAS TROWBRIDGE