17620-17622 W RAYMER ST 91325

Certificate Information: 17620-17622 W RAYMER ST 91325

Application / Permit
25016-20000-01883
Plan Check / Job No.
B25VN01558
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE AND PORTION OF (E) SFD INTO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22.
Permit Issued
Issued on 3/6/2025
Issuing Office
Current Status
CofO Issued on 6/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2025 APPLICANT
Assigned to Plan Check Engineer 1/29/2025 ISIS ARGUETA
Corrections Issued 1/29/2025 ISIS ARGUETA
Applicant returned to address corrections 2/12/2025 ISIS ARGUETA
Plan Check Approved 2/19/2025 NAREG ATARIAN
Issued 3/6/2025 APPLICANT
CofO in Progress 6/18/2025 NICHOLAS TROWBRIDGE
Permit Finaled 6/27/2025 RUBEN SALAS
CofO Issued 6/27/2025 RUBEN SALAS
Permit Finaled 6/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/31/2025 CARLOS AGUILERA
Sewer availability Cleared 1/31/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/3/2025 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/26/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/26/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 3/26/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/9/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/9/2025 Corrections Issued NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 4/14/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 4/14/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/14/2025 Approved NICHOLAS TROWBRIDGE
Sewer 4/15/2025 Approved NICHOLAS TROWBRIDGE
Underground Mechanical 4/15/2025 Approved NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Approved NICHOLAS TROWBRIDGE
Wood Frame 4/21/2025 Approved NICHOLAS TROWBRIDGE
Insulation 4/24/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 4/29/2025 Approved KEVIN BERBERYAN
Drywall Nailing 4/29/2025 Approved KEVIN BERBERYAN
Green Building Rough 4/29/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 4/30/2025 Approved KEVIN BERBERYAN
Shower Pan 4/30/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 6/11/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 6/11/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 6/11/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Final 6/11/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Final 6/11/2025 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 6/11/2025 SGSOV Approved NICHOLAS TROWBRIDGE
Smoke Detectors 6/11/2025 Approved NICHOLAS TROWBRIDGE
Final 6/17/2025 OK to Issue CofO NICHOLAS TROWBRIDGE
Green Building Final 6/17/2025 Approved NICHOLAS TROWBRIDGE