3431 S ALSACE AVE 90016
Certificate Information: 3431 S ALSACE AVE 90016
- Application / Permit
- 25016-20000-01431
- Plan Check / Job No.
- B25VN01183
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/29/2025
- Issuing Office
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 1/25/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/28/2025 | APPLICANT |
| Plan Check Approved | 1/29/2025 | ROSENDO MEDINA |
| Issued | 1/29/2025 | APPLICANT |
| CofO in Progress | 6/6/2025 | ARTHUR NEGRETE |
| CofO in Progress | 6/6/2025 | ARTHUR NEGRETE |
| Permit Finaled | 6/10/2025 | DEROLD HAUFF |
| CofO Issued | 6/10/2025 | DEROLD HAUFF |
| Permit Finaled | 6/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 1/27/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 1/27/2025 | DAVID LOPEZ |
Contact Information
| Contractor | Neo Builders And Design Inc; Lic. No.: 1114778-B | 12005 ALBERS APT 233 NORTH HOLLYWOOD, CA 91607 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/21/2025 | Approved | ARTHUR NEGRETE |
| Deputy Drilled-In Anchors | 2/24/2025 | Conditional Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/24/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 3/10/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 3/12/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 3/12/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 3/12/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Rough | 3/12/2025 | Approved | ARTHUR NEGRETE |
| Wood Frame | 3/12/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Insulation | 3/17/2025 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 3/17/2025 | Partial Inspection | ALEX COLIN |
| BUILDING-Rough-Frame | 3/18/2025 | Partial Approval | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 3/18/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Shower Pan | 3/18/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Special/Order Compliance | 3/18/2025 | Partial Inspection | ALEX COLIN |
| Shower Pan | 3/20/2025 | Not Ready for Inspection | REGINA MENDEZ |
| Shower Pan | 3/25/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 3/26/2025 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 4/1/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 4/1/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 5/9/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 5/14/2025 | Approved | ARTHUR NEGRETE |
| Final | 5/14/2025 | Partial Inspection | ARTHUR NEGRETE |
| Green Building Final | 5/14/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Rough | 5/14/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 5/14/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 5/14/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/14/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 5/14/2025 | Approved | ARTHUR NEGRETE |
| Final | 6/6/2025 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 6/6/2025 | Approved | ARTHUR NEGRETE |