3431 S ALSACE AVE 90016

Certificate Information: 3431 S ALSACE AVE 90016

Application / Permit
25016-20000-01431
Plan Check / Job No.
B25VN01183
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 1/29/2025
Issuing Office
Current Status
CofO Issued on 6/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2025 APPLICANT
Assigned to Plan Check Engineer 1/23/2025 JEROME MAGAT PALMA
Corrections Issued 1/25/2025 JEROME MAGAT PALMA
Building Plans Picked Up 1/28/2025 APPLICANT
Plan Check Approved 1/29/2025 ROSENDO MEDINA
Issued 1/29/2025 APPLICANT
CofO in Progress 6/6/2025 ARTHUR NEGRETE
CofO in Progress 6/6/2025 ARTHUR NEGRETE
Permit Finaled 6/10/2025 DEROLD HAUFF
CofO Issued 6/10/2025 DEROLD HAUFF
Permit Finaled 6/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/27/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 1/27/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 1/27/2025 DAVID LOPEZ
Sewer availability Cleared 1/27/2025 DAVID LOPEZ

Contact Information

Contractor Neo Builders And Design Inc; Lic. No.: 1114778-B 12005 ALBERS APT 233      NORTH HOLLYWOOD, CA 91607

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/21/2025 Approved ARTHUR NEGRETE
Deputy Drilled-In Anchors 2/24/2025 Conditional Approval STUART CHAPMAN
Footing/Foundation/Slab 2/24/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 3/10/2025 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 3/12/2025 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Rough 3/12/2025 Approved ARTHUR NEGRETE
Green Building Rough 3/12/2025 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Rough 3/12/2025 Approved ARTHUR NEGRETE
Wood Frame 3/12/2025 Not Ready for Inspection ARTHUR NEGRETE
Insulation 3/17/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/17/2025 Partial Inspection ALEX COLIN
BUILDING-Rough-Frame 3/18/2025 Partial Approval ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 3/18/2025 Not Ready for Inspection ARTHUR NEGRETE
Shower Pan 3/18/2025 Not Ready for Inspection ARTHUR NEGRETE
Special/Order Compliance 3/18/2025 Partial Inspection ALEX COLIN
Shower Pan 3/20/2025 Not Ready for Inspection REGINA MENDEZ
Shower Pan 3/25/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 3/26/2025 Approved ARTHUR NEGRETE
Drywall Nailing 4/1/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 4/1/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 5/9/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 5/14/2025 Approved ARTHUR NEGRETE
Final 5/14/2025 Partial Inspection ARTHUR NEGRETE
Green Building Final 5/14/2025 Not Ready for Inspection ARTHUR NEGRETE
Green Building Rough 5/14/2025 Approved ARTHUR NEGRETE
HVAC-Final 5/14/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 5/14/2025 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 5/14/2025 Approved ARTHUR NEGRETE
Final 6/6/2025 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 6/6/2025 Approved ARTHUR NEGRETE