170 N VISTA ST 90036
Certificate Information: 170 N VISTA ST 90036
- Application / Permit
- 25016-20000-01155
- Plan Check / Job No.
- B25VN00956
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel two story SFD, removing and adding interior walls, removing and adding windows, relocating bathrooms, and kitchen, and add new skylights
- Permit Issued
- Issued on 3/12/2025
- Issuing Office
- Metro
- Current Status
- Issued on 3/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | NAREG ATARIAN |
| Corrections Issued | 1/18/2025 | NAREG ATARIAN |
| Quality Review Completed | 1/23/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 1/27/2025 | APPLICANT |
| Plan Check Approved | 2/14/2025 | NAREG ATARIAN |
| Issued | 3/12/2025 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 2/12/2025 | JORGE RUIZ |
| HPOZ | Cleared | 2/12/2025 | JORGE RUIZ |
| Miscellaneous | Cleared | 2/12/2025 | JORGE RUIZ |
| ZI | Cleared | 2/12/2025 | JORGE RUIZ |
Contact Information
| Contractor | Zumwalt Development Inc; Lic. No.: 1097342-B | 2980 ALLESANDRO ST APT 210 LOS ANGELES, CA 90039 |
| Engineer | Azarbin,, Hamid; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/14/2025 | Conditional Approval | JOSE MACIAS |
| ELECTRICAL-Rough | 4/29/2025 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 4/29/2025 | Not Ready for Inspection | JOSE MACIAS |
| Underground Mechanical | 4/29/2025 | Approved | JOSE MACIAS |
| Wood Frame | 4/29/2025 | Not Ready for Inspection | JOSE MACIAS |
| Light Gage Steel Frame | 5/7/2025 | No Access for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 5/9/2025 | Corrections Issued | WAYNE REGESTER |
| HVAC-Rough | 5/9/2025 | Corrections Issued | WAYNE REGESTER |
| PLUMBING-Rough | 5/9/2025 | Corrections Issued | WAYNE REGESTER |
| Wood Frame | 5/9/2025 | Corrections Issued | WAYNE REGESTER |
| ELECTRICAL-Rough | 5/21/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 5/21/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 5/21/2025 | Approved | JOSE MACIAS |
| Wood Frame | 5/21/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 5/22/2025 | Approved | JOSE MACIAS |
| Deputy Wood Construction | 5/22/2025 | Conditional Approval | JOSE MACIAS |
| Green Building Rough | 5/22/2025 | Approved | JOSE MACIAS |
| METHANE-Rough | 5/22/2025 | Approved | JOSE MACIAS |
| Insulation | 5/27/2025 | Approved | JOSE MACIAS |
| Drywall Nailing | 6/4/2025 | Approved | JOSE MACIAS |
| Light Gage Steel Frame | 6/5/2025 | No Access for Inspection | JOSE MACIAS |
| Shower Pan | 7/1/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 7/3/2025 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 7/15/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 7/17/2025 | Corrections Issued | JOSH MEISTER |
| Interior/Exterior Lathing | 7/21/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 8/7/2025 | Approved | JOSE MACIAS |
| Gas Test | 10/21/2025 | Approved | JOSH MEISTER |
| PLUMBING-Final | 10/21/2025 | Not Ready for Inspection | JOSH MEISTER |