905 1/2 E 98TH ST 90002

Certificate Information: 905 1/2 E 98TH ST 90002

Application / Permit
25016-20000-00928
Plan Check / Job No.
B25VN00709
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). PER WFPP.
Permit Issued
Issued on 1/23/2025
Issuing Office
Current Status
CofO in Progress on 5/14/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/14/2025 APPLICANT
Assigned to Plan Check Engineer 1/17/2025 JEROME MAGAT PALMA
Corrections Issued 1/18/2025 JEROME MAGAT PALMA
Building Plans Picked Up 1/22/2025 APPLICANT
Issued 1/23/2025 APPLICANT
CofO in Progress 5/14/2026 ARTHUR NEGRETE

Permit Application Clearance Information

Address approval Cleared 1/22/2025 RYAN CASTRO
Sewer availability Cleared 1/22/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/23/2025 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/27/2025 Conditional Approval ANTHONY EGSON
Footing/Foundation/Slab 6/6/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 6/6/2025 Partial Approval ANTHONY EGSON
Sewer 6/6/2025 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 7/8/2025 Approved ANTHONY EGSON
Deputy Drilled-In Anchors 9/19/2025 Conditional Approval ANTHONY EGSON
BUILDING-Rough-Frame 10/3/2025 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 12/2/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 12/2/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 12/2/2025 Approved ARTHUR NEGRETE
Gas Test 12/2/2025 Approved ARTHUR NEGRETE
Green Building Rough 12/2/2025 Approved ARTHUR NEGRETE
HVAC-Rough 12/2/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 12/2/2025 Approved ARTHUR NEGRETE
Insulation 1/2/2026 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 1/2/2026 Approved ARTHUR NEGRETE
Drywall Nailing 1/6/2026 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 1/6/2026 Approved ARTHUR NEGRETE
Shower Pan 1/6/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 3/10/2026 Approved ARTHUR NEGRETE
Gas Test 3/10/2026 Approved ARTHUR NEGRETE
Service/Power Release 3/10/2026 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Final 4/9/2026 Approved ARTHUR NEGRETE
Final 4/9/2026 Corrections Issued ARTHUR NEGRETE
Green Building Final 4/9/2026 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Final 4/9/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 4/9/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 4/9/2026 Approved ARTHUR NEGRETE
Smoke Detectors 4/9/2026 Approved ARTHUR NEGRETE
Final 5/6/2026 Corrections Issued ARTHUR NEGRETE
Green Building Final 5/6/2026 Approved ARTHUR NEGRETE
Service/Power Release 5/6/2026 Not Ready for Inspection ARTHUR NEGRETE
Final 5/13/2026 OK to Issue CofO ARTHUR NEGRETE
Service/Power Release 5/13/2026 Approved ARTHUR NEGRETE