20140 W RINALDI ST 130 91326

Certificate Information: 20140 W RINALDI ST 130 91326

Application / Permit
25016-20000-00752
Plan Check / Job No.
B25VN00585
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
TI of a Coffee shop in a core and shell building
Permit Issued
Issued on 4/28/2025
Issuing Office
Current Status
CofO Issued on 2/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2025 APPLICANT
Assigned to Plan Check Engineer 1/15/2025 SARKIS HARABEDIAN
Corrections Issued 1/16/2025 SARKIS HARABEDIAN
Applicant returned to address corrections 4/23/2025 KAVIAN REFAHI
Plan Check Approved 4/27/2025 SARKIS HARABEDIAN
Issued 4/28/2025 APPLICANT
Permit Finaled 2/25/2026 JEFFREY DURAN
Permit Finaled 2/25/2026 JEFFREY DURAN
CofO Issued 2/25/2026 JEFFREY DURAN

Permit Application Clearance Information

Sewer availability Cleared 1/22/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/22/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/23/2025 LEE GUILBEAUX
Specific Plan Cleared 2/12/2025 OLGA AYALA
Food establishment approval Cleared 4/27/2025 LACDHS APPROVED

Contact Information

Architect Moradi, Owrang, Sheida; Lic. No.: C35621 4774 PARK GRANADA #9354      CALABASAS, CA 91372
Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/5/2025 Partial Inspection DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 10/9/2025 Approved DEANDRE HOFFMAN
Drywall Nailing 10/15/2025 Partial Approval DEANDRE HOFFMAN
Insulation 10/15/2025 Approved DEANDRE HOFFMAN
Special/Order Compliance 10/15/2025 Corrections Issued DEANDRE HOFFMAN
Light Gage Steel Frame 10/27/2025 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 11/7/2025 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 11/13/2025 Approved DEANDRE HOFFMAN
Light Gage Steel Frame 11/26/2025 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 12/2/2025 Approved DEANDRE HOFFMAN
Special/Order Compliance 12/2/2025 Partial Inspection IAN BLINN
T-Bar Ceiling 12/10/2025 Not Ready for Inspection DEANDRE HOFFMAN
Final 2/19/2026 Conditional Approval EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 2/19/2026 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 2/19/2026 Approved EDWIN GREGORYONA