19330 W VENTURA BLVD 91356
Certificate Information: 19330 W VENTURA BLVD 91356
- Application / Permit
- 25016-20000-00723
- Plan Check / Job No.
- B24VN27331
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- eplan: Structural repairs to a two-story commercial building following vehicle impact damage. Scope includes restoration of the moment frame system at the northwest corner, where damage is localized and removal and replace of curtain wall.
- Permit Issued
- Issued on 7/23/2025
- Issuing Office
- Current Status
- Issued on 7/23/2025
Permit Application Status History
| Submitted | 1/16/2025 | APPLICANT |
| Assigned to Zoning Architect | 1/23/2025 | LY CHEA |
| Assigned to Plan Check Engineer | 1/30/2025 | HERNAN ARREOLA |
| Corrections Issued | 2/3/2025 | KESETE HAREGOT |
| Quality Review Completed | 2/11/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/20/2025 | KESETE HAREGOT |
| Plan Check Approved | 7/21/2025 | HERNAN ARREOLA |
| Issued | 7/23/2025 | APPLICANT |
Permit Application Clearance Information
| "D" conditions | Cleared | 2/10/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 2/10/2025 | DANIEL CORONADO |
| ZA Case | Cleared | 2/10/2025 | DANIEL CORONADO |
| Specific Plan | Cleared | 3/19/2025 | ABRAHAM LAMONTAGNE |
| DAS Clearance | Cleared | 6/30/2025 | Aung Soe |
| Zoning Plan Check | Cleared | 7/8/2025 | Aung Soe |
Contact Information
| Architect | Bannick,, Arthur Joseph; Lic. No.: NA17986 | , |
| Contractor | Repipe 1; Lic. No.: 927892-B | , |
| Contractor | Ultimate Builders Inc; Lic. No.: 927892-B | , |
| Engineer | Ding,, Wenzhuo; Lic. No.: C82891 | 5205 SUNNY POINT PL RANCHO PALOS VERDES, CA 90275 |
| Engineer | Ding,, Wenzhuo; Lic. No.: NA82891 | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/4/2025 | Corrections Issued | JOHN KITCKO |
| Footing/Foundation/Slab | 12/4/2025 | Not Ready for Inspection | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 12/16/2025 | Corrections Issued | BRIAN KELLY |
| Footing/Foundation/Slab | 12/16/2025 | Partial Inspection | BRIAN KELLY |
| Footing/Foundation/Slab | 1/16/2026 | Partial Approval | BRIAN KELLY |
| Structural Steel Frame | 1/23/2026 | Partial Approval | BRIAN KELLY |
| Wood Frame | 1/23/2026 | Partial Approval | BRIAN KELLY |
| Insulation | 1/30/2026 | Approved | BRIAN KELLY |
| Drywall Nailing | 2/3/2026 | Approved | BRIAN KELLY |
| Special/Order Compliance | 2/11/2026 | Partial Inspection | BRIAN KELLY |
| Interior/Exterior Lathing | 7/22/2026 | Approved | BRIAN KELLY |