4903 N AZUCENA DR 91364

Certificate Information: 4903 N AZUCENA DR 91364

Application / Permit
25016-20000-00669
Plan Check / Job No.
B24VN27327
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE TO A DETACHED ACCESSORY DWELLING UNIT PER GC 66323(a)(1). NFPA 13D FIRE SPRINKLER SYSTEM IS REQUIRED
Permit Issued
Issued on 8/1/2025
Issuing Office
Current Status
Issued on 8/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/9/2025 APPLICANT
Assigned to Plan Check Engineer 1/13/2025 CARLOS MONTES
Corrections Issued 1/14/2025 CARLOS MONTES
Applicant returned to address corrections 4/25/2025 CARLOS MONTES
Applicant returned to address corrections 4/28/2025 NGHI SU
Plan Check Approved 6/4/2025 CARLOS MONTES
Issued 8/1/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/5/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 2/5/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/5/2025 BIAINA HARITUNIAN
Specific Plan Cleared 2/11/2025 JUDE HERNANDEZ
Hydrant and Access approval Cleared 4/3/2025 FRANK GOMEZ
Grading Pre-Inspection Cleared 4/26/2025 CARLOS MONTES

Contact Information

Contractor Ali R Markazi Construction; Lic. No.: 1010726-B       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 8/5/2025 Conditional Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/5/2025 Corrections Issued JOHN HAYES
PLUMBING-Rough 8/5/2025 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 8/11/2025 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/12/2025 Corrections Issued SCOTT SOBEL
PLUMBING-Rough 8/12/2025 Partial Approval SCOTT SOBEL
Sewer 8/12/2025 Approved SCOTT SOBEL
Excavation/Setback/Form/Re-Bar 8/21/2025 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 8/21/2025 Corrections Issued JOHN HAYES
Deputy Drilled-In Anchors 8/22/2025 Conditional Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/25/2025 Approved JOHN KIDWELL
Footing/Foundation/Slab 8/25/2025 Approved JOHN KIDWELL
Deputy Wood Construction 8/29/2025 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 9/2/2025 Not Ready for Inspection JOHN HAYES
Green Building Rough 9/2/2025 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 9/2/2025 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 9/25/2025 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Partial Approval JOHN KIDWELL
Green Building Rough 9/25/2025 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 9/25/2025 Approved JOHN KIDWELL
PLUMBING-Rough 9/25/2025 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 9/25/2025 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 10/7/2025 Partial Approval SCOTT SOBEL
Shower Pan 10/7/2025 Approved SCOTT SOBEL
Insulation 12/3/2025 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 12/10/2025 Approved JOHN HAYES
Green Building Rough 12/10/2025 Approved JOHN HAYES
Insulation 12/10/2025 Approved JOHN HAYES
Special/Order Compliance 12/10/2025 Corrections Issued JOHN HAYES
Verify Sprinkler Sign Off 12/10/2025 Approved JOHN HAYES
Drywall Nailing 12/12/2025 Approved ROBERT GOLD
Final 4/2/2026 Corrections Issued JOHN HAYES
Green Building Final 4/2/2026 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 4/2/2026 SGSOV Not Ready JOHN HAYES
Smoke Detectors 4/2/2026 Not Ready for Inspection JOHN HAYES
Final 4/9/2026 Corrections Issued JOHN HAYES
Green Building Final 4/9/2026 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Not Required JOHN HAYES
Smoke Detectors 4/9/2026 Approved JOHN HAYES
Special/Order Compliance 4/9/2026 Partial Inspection SEAN WIRCH
Final 4/14/2026 Corrections Issued JOHN HAYES
Green Building Final 4/14/2026 Approved JOHN HAYES
Special/Order Compliance 4/24/2026 Partial Approval JOHN HAYES