5246 N BEEMAN AVE 91607
Certificate Information: 5246 N BEEMAN AVE 91607
- Application / Permit
- 25016-20000-00633
- Plan Check / Job No.
- B25VN00498
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. PROPOSED ADDITION TO (E) SINGLE FAMILY DWELLING AND MAJOR REMODEL. ALL WORK PER ENGINEERING. ** NFPA_13D FIRE SPRINKLERS THRU-OUT**
- Permit Issued
- Issued on 2/24/2025
- Issuing Office
- Current Status
- CofO Issued on 3/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 1/25/2025 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 2/6/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 2/22/2025 | SARKIS HARABEDIAN |
| Issued | 2/24/2025 | APPLICANT |
| CofO in Progress | 2/20/2026 | OGANES TARAKHCHYAN |
| Permit Finaled | 3/18/2026 | RUBEN SALAS |
| CofO Issued | 3/18/2026 | RUBEN SALAS |
| Permit Finaled | 3/18/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/31/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/3/2025 | CARLOS AGUILERA |
| Specific Plan | Cleared | 2/3/2025 | JOANNA MARROQUIN |
| Miscellaneous | Cleared | 2/5/2025 | DAVID URITA |
Contact Information
| Contractor | Susan Development And Construction Inc; Lic. No.: 1089492-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/17/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 4/17/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 4/18/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 4/24/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Partial Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 5/20/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Sewer | 5/22/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2025 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/8/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 8/8/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/8/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/18/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 8/18/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/18/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 8/20/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/26/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 2/9/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 2/9/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/9/2026 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 2/9/2026 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 2/9/2026 | Approved | OGANES TARAKHCHYAN |
| Final | 2/19/2026 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 2/19/2026 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 2/19/2026 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 2/19/2026 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 2/19/2026 | Approved | OGANES TARAKHCHYAN |