15655-15657 W SIMONDS ST 91344

Certificate Information: 15655-15657 W SIMONDS ST 91344

Application / Permit
25016-20000-00432
Plan Check / Job No.
B25VN00351
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/24/2025
Issuing Office
Current Status
CofO Issued on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2025 APPLICANT
Assigned to Plan Check Engineer 1/15/2025 GURUNATH NESARAJAH
Corrections Issued 1/16/2025 GURUNATH NESARAJAH
Plan Check Approved 1/30/2025 GURUNATH NESARAJAH
Issued 2/24/2025 APPLICANT
CofO in Progress 7/3/2025 JENNIFER RABUCHIN
CofO in Progress 7/8/2025 JENNIFER RABUCHIN
Permit Finaled 7/22/2025 RUBEN SALAS
CofO Issued 7/22/2025 RUBEN SALAS
Permit Finaled 7/22/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/17/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/17/2025 EDGAR ALCARAZ
Sewer availability Cleared 1/17/2025 EDGAR ALCARAZ
Grading Pre-Inspection Cleared 1/20/2025 CHARLES POWELL

Contact Information

Contractor Carlos Anaya; Lic. No.: 1034169-B       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/28/2025 Partial Approval JAVIER RAMOS JR
Sewer 3/28/2025 Approved JAVIER RAMOS JR
Underground Mechanical 3/28/2025 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 4/3/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 4/4/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/18/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 4/18/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 4/18/2025 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 4/18/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/18/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 4/22/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 4/22/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/22/2025 Approved NICHOLAS TROWBRIDGE
Sewer 4/22/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 4/24/2025 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 4/24/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/30/2025 Approved JENNIFER RABUCHIN
Green Building Rough 4/30/2025 Approved JENNIFER RABUCHIN
Underground Mechanical 4/30/2025 Partial Approval JENNIFER RABUCHIN
Insulation 5/2/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Approved JENNIFER RABUCHIN
Shower Pan 5/7/2025 Approved LOUIS ESCOTO
Drywall Nailing 5/14/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 5/14/2025 Approved MICHAEL CORTEZ
Final 6/25/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 6/25/2025 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 6/25/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 6/25/2025 Approved JENNIFER RABUCHIN
Final 7/2/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 7/2/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 7/3/2025 Approved JENNIFER RABUCHIN
Final 7/3/2025 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 7/3/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/3/2025 Approved JENNIFER RABUCHIN
Service/Power Release 7/3/2025 Not Ready for Inspection JENNIFER RABUCHIN