21860 W BURBANK BLVD #360 91367
Certificate Information: 21860 W BURBANK BLVD #360 91367
- Application / Permit
- 25016-20000-00259
- Plan Check / Job No.
- B25VN00172
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Dental Clinic
- Work Description
- CHANGE OF USE FROM OFFICE TO DENTAL OFFICE & NON-STRUCTURAL TENANT IMPROVEMENT: DEMO & INSTALL NON-BEARING PARTITION WALLS **ePlan**
- Permit Issued
- Issued on 5/5/2025
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2025 | NILOOFAR MEHRAIN |
| Assigned to Zoning Architect | 1/9/2025 | RONALD GREENE |
| Corrections Issued | 1/12/2025 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/24/2025 | STEVEN KIM |
| Applicant returned to address corrections | 2/18/2025 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/2/2025 | NILOOFAR MEHRAIN |
| Plan Check Approved | 5/5/2025 | NILOOFAR MEHRAIN |
| Issued | 5/5/2025 | APPLICANT |
| CofO in Progress | 7/7/2025 | BRIAN KELLY |
| Permit Finaled | 7/8/2025 | JEFFREY DURAN |
| CofO Issued | 7/8/2025 | JEFFREY DURAN |
| Permit Finaled | 7/8/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 1/21/2025 | Kelvin Chuong |
| ZI | Cleared | 3/10/2025 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 4/23/2025 | NATHAN ROMINE |
| Specific Plan | Cleared | 4/23/2025 | NATHAN ROMINE |
| Specific Plan | Cleared | 4/23/2025 | SHEILA AHORAIAN |
| Zoning Plan Check | Cleared | 4/30/2025 | Ronald Greene |
Contact Information
| Architect | Miguel,, Miguel Maximo; Lic. No.: C13612 | 2214 GRAFTON STREET SIMI VALLEY, CA 93063 |
| Contractor | Gfi Construction Inc; Lic. No.: 762312-B | , |
| Contractor | Gfi Electrical; Lic. No.: 762312-B | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 5/9/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Pre-Inspection | 5/9/2025 | Approved | DEANDRE HOFFMAN |
| T-Bar Ceiling | 5/9/2025 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 5/15/2025 | Approved | BRIAN KELLY |
| Final | 6/18/2025 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Concrete Frame | 6/18/2025 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Masonry Frame | 6/18/2025 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 6/18/2025 | Not Ready for Inspection | BRIAN KELLY |
| Final | 6/23/2025 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Concrete Frame | 6/23/2025 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Masonry Frame | 6/23/2025 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 6/23/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 6/23/2025 | Not Ready for Inspection | BRIAN KELLY |
| Special/Order Compliance | 6/24/2025 | Partial Inspection | BRIAN KELLY |
| Final | 6/25/2025 | OK to Issue CofO | BRIAN KELLY |
| Reinforced Concrete Frame | 6/25/2025 | Approved | BRIAN KELLY |
| Reinforced Masonry Frame | 6/25/2025 | Approved | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 6/25/2025 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 6/25/2025 | Approved | BRIAN KELLY |