6207 1/2 N WILLOW CREST AVE 91606
Certificate Information: 6207 1/2 N WILLOW CREST AVE 91606
- Application / Permit
- 25016-20000-00015
- Plan Check / Job No.
- B24VN27257
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERT EXISTING DETACHED GARAGE AND EXISITING 14'-3" X 18'-3' UNPERMITTED STRUCTURE BUILT PROIR TO JAN 1 2020 TO AN ADU
- Permit Issued
- Issued on 2/25/2025
- Issuing Office
- Current Status
- CofO Issued on 2/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2025 | FERNANDO FLORES |
| Corrections Issued | 1/9/2025 | FERNANDO FLORES |
| Applicant returned to address corrections | 1/29/2025 | LAWRENCE QUIRANTE |
| Plan Check Approved | 2/15/2025 | FERNANDO FLORES |
| Issued | 2/25/2025 | APPLICANT |
| CofO in Progress | 1/2/2026 | JOSE AVILA |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
| CofO Issued | 2/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Hold | Cleared | 1/30/2025 | CARMEN MERAZ |
| Address approval | Cleared | 2/4/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 2/4/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 2/11/2025 | BIAINA HARITUNIAN |
| ZA Case | Cleared | 2/13/2025 | DAVID URITA |
Contact Information
| Contractor | R L Remodeling Inc; Lic. No.: 885032-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/12/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 3/12/2025 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 3/17/2025 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 3/17/2025 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 6/24/2025 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 6/27/2025 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 7/10/2025 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 7/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 7/30/2025 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 7/30/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 8/12/2025 | Not Ready for Inspection | JOSE AVILA |
| Deputy Wood Construction | 8/25/2025 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/25/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 8/25/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 8/25/2025 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 8/28/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 8/28/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 9/2/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 9/2/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 9/2/2025 | Approved | JOSE AVILA |
| Insulation | 9/4/2025 | Corrections Issued | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/4/2025 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 9/4/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 9/4/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/15/2025 | Approved | JOSE AVILA |
| Insulation | 9/15/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 9/15/2025 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 9/17/2025 | Approved | JOSE AVILA |
| Special/Order Compliance | 9/29/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 11/17/2025 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 11/17/2025 | Approved | JOSE AVILA |
| HVAC-Final | 11/17/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 11/17/2025 | Corrections Issued | JOSE AVILA |
| Final | 11/24/2025 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/24/2025 | SGSOV Not Ready | JOSE AVILA |
| ELECTRICAL-Final | 12/8/2025 | Approved | JOSE AVILA |
| Final | 12/8/2025 | Corrections Issued | JOSE AVILA |
| Green Building Final | 12/8/2025 | Approved | JOSE AVILA |
| HVAC-Final | 12/8/2025 | Approved | JOSE AVILA |
| PLUMBING-Final | 12/8/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 12/8/2025 | Approved | JOSE AVILA |
| Final | 12/17/2025 | Corrections Issued | JOSE AVILA |
| Final | 12/23/2025 | Not Ready for Inspection | JOSE AVILA |
| Final | 12/31/2025 | OK to Issue CofO | JOSE AVILA |