1526 S MALCOLM AVE 90024
Certificate Information: 1526 S MALCOLM AVE 90024
- Application / Permit
- 25016-10001-06429
- Plan Check / Job No.
- B25LA17699
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO 25016-10000-06429 ADDITION TO (E) SFD.
- Permit Issued
- Issued on 6/26/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2025 | SUNMIN LEE |
| Corrections Issued | 5/8/2025 | SUNMIN LEE |
| Building Plans Picked Up | 5/15/2025 | APPLICANT |
| Plan Check Approved | 6/26/2025 | CRISTINA SALAZAR |
| Issued | 6/26/2025 | APPLICANT |
| CofO in Progress | 11/5/2025 | MICHAEL ALLEN |
| Permit Finaled | 11/29/2025 | RICHARD STEINBACH |
| CofO Issued | 11/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/27/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 5/29/2025 | MICHAEL BROWN |
| Specific Plan | Cleared | 5/29/2025 | JOSHUA JONES |
| Grading Pre-Inspection | Cleared | 6/23/2025 | SUNMIN LEE |
Contact Information
| Contractor | Ecobuild Pros Inc; Lic. No.: 1111889-B | 14127 MARGATE ST SHERMAN OAKS, CA 91401 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/23/2025 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 7/24/2025 | Conditional Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/1/2025 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 8/1/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/1/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Conditional Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/20/2025 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/20/2025 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 8/20/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 8/20/2025 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/20/2025 | Approved | ARAM AVEDISIAN |
| Shower Pan | 8/20/2025 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/25/2025 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 8/25/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 8/25/2025 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 9/2/2025 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 9/2/2025 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | MICHAEL ALLEN |
| Final | 10/23/2025 | Corrections Issued | MICHAEL ALLEN |
| Footing/Foundation/Slab | 10/23/2025 | Approved | MICHAEL ALLEN |
| Green Building Final | 10/23/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 10/23/2025 | Approved | MICHAEL ALLEN |
| Smoke Detectors | 10/23/2025 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Final | 11/4/2025 | Approved | MICHAEL ALLEN |
| Final | 11/4/2025 | OK to Issue CofO | MICHAEL ALLEN |
| HVAC-Final | 11/4/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 11/4/2025 | Approved | MICHAEL ALLEN |
| Smoke Detectors | 11/4/2025 | Approved | MICHAEL ALLEN |