5500 W WILSHIRE BLVD 90036
Certificate Information: 5500 W WILSHIRE BLVD 90036
- Application / Permit
- 25016-10000-37965
- Plan Check / Job No.
- B25LA54990
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- (ePLAN) NDC-2206 - Phase 2 Non-Ductile Concrete retrofit to wings of existing building, compliance with Division 95.
- Permit Issued
- Issued on 4/28/2026
- Issuing Office
- Current Status
- Issued on 4/28/2026
Permit Application Status History
| Submitted | 1/7/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2026 | VICTOR CHEN |
| Assigned to Zoning Architect | 1/30/2026 | ALIZA NAZIR |
| Corrections Issued | 2/9/2026 | VICTOR CHEN |
| Quality Review Completed | 2/23/2026 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 3/19/2026 | VICTOR CHEN |
| Applicant returned to address corrections | 3/25/2026 | VICTOR CHEN |
| Applicant returned to address corrections | 4/10/2026 | VICTOR CHEN |
| Applicant returned to address corrections | 4/20/2026 | VICTOR CHEN |
| Plan Check Approved | 4/28/2026 | VICTOR CHEN |
| Issued | 4/28/2026 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 3/6/2026 | ALEX VELA |
| Supp. Use District POD/CDO/TDO | Cleared | 3/16/2026 | RYAN LY |
| Green Code | Cleared | 3/20/2026 | AARON COSTA |
| Zoning Plan Check | Cleared | 3/23/2026 | ALIZA NAZIR |
| DAS Clearance | Cleared | 4/20/2026 | Daniel Chan |
Contact Information
| Architect | Algaze,, Nelson; Lic. No.: C21090 | 1524 1ST STREET MANHATTAN BEACH, CA 90266 |
| Contractor | Owner-Builder | , |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/5/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 5/6/2026 | Partial Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 5/6/2026 | Partial Approval | RAFAEL CORTES |
| Special/Order Compliance | 5/6/2026 | Partial Approval | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 5/8/2026 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Footing/Foundation/Slab | 5/8/2026 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2026 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Wood Frame | 5/19/2026 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 5/22/2026 | Partial Approval | IAN BLINN |
| Footing/Foundation/Slab | 5/22/2026 | Partial Approval | IAN BLINN |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2026 | Partial Approval | MARTIN TAVITIAN |
| Reinforced Concrete Frame | 6/18/2026 | Partial Approval | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2026 | Partial Approval | PAUL BAZERKANIAN |