700 WORLD WAY Terminal 7 90045

Certificate Information: 700 WORLD WAY Terminal 7 90045

Application / Permit
25016-10000-37872
Plan Check / Job No.
B25LA54766
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(3) Airport Building
Work Description
**ePlan**LAX** THE SCOPE OF THIS PROJECT IS THE REPLACEMENT AND UPGRADE OF TRANSPORTATION SECURITY SCREENING EQUIPMENT (TSE). THIS SCOPE OF WORK IS LIMITED TO THE REPLACEMENT OF TSA TSE, ELECTRICAL AND DATA UPGRADES FOR THE EQUIPMENT AND SEISMIC ANCHORING OF THE EQUIPMENT. NO CHANGES TO THE STRUCTURE, OCCUPANCY, OR EGRESS AS PART OF THE EQUIPMENT REMOVAL OR INSTALLATION.
Permit Issued
Issued on 5/7/2026
Issuing Office
Current Status
Issued on 5/7/2026

Permit Application Status History

Submitted 12/30/2025 APPLICANT
Assigned to Plan Check Engineer 1/8/2026 VARAND SARKISIAN
Corrections Issued 1/15/2026 VARAND SARKISIAN
Quality Review Completed 1/15/2026 LIPING TENG
Plan Check Approved 3/4/2026 VARAND SARKISIAN
Issued 5/7/2026 APPLICANT

Permit Application Clearance Information

City owned building/parcel Cleared 1/13/2026 MASON NG
Project Permit Cleared 1/20/2026 ALEXANDER GARCIA
DAS Clearance Cleared 2/12/2026 Lily Teng
Airport buildings Cleared 2/14/2026 ANDREW KO

Contact Information

Architect Lengyel,, Aaron William; Lic. No.: NA39679       ,
Contractor Leidos Db Inc; Lic. No.: 872860-B       ,
Engineer Wilkinson,, Craig; Lic. No.: NA6705       ,

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI