13273 W VENTURA BLVD 91604
Certificate Information: 13273 W VENTURA BLVD 91604
- Application / Permit
- 25016-10000-37738
- Plan Check / Job No.
- B25LA54561
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Cafe
- Work Description
- EPLAN TI AND CHANGE OF USE FROM OFFICE TO CAFE AND COFFEE SHOP
- Permit Issued
- Issued on 4/28/2026
- Issuing Office
- Current Status
- Issued on 4/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/29/2025 | APPLICANT |
| Assigned to Zoning Architect | 1/2/2026 | LINGHUI YU |
| Assigned to Plan Check Engineer | 1/8/2026 | JOSEPH RAFOLS |
| Corrections Issued | 1/14/2026 | JOSEPH RAFOLS |
| Quality Review Completed | 2/2/2026 | HERNAN ARREOLA |
| Applicant returned to address corrections | 3/18/2026 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 3/26/2026 | JOSEPH RAFOLS |
| Plan Check Approved | 4/28/2026 | JOSEPH RAFOLS |
| Issued | 4/28/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2026 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/17/2026 | LEE GUILBEAUX |
| DAS Clearance | Cleared | 3/18/2026 | Samuel Gonzalez |
| Specific Plan | Cleared | 3/25/2026 | MIGUEL CRISOSTOMO |
| Specific Plan | Cleared | 4/2/2026 | JOANNA MARROQUIN |
| Zoning Plan Check | Cleared | 4/3/2026 | LINGHUI YU |
| Food Service Establishment | Cleared | 4/16/2026 | ANSON PUA |
| Green Code | Cleared | 4/22/2026 | Samuel Gonzalez |
| Food establishment approval | Cleared | 4/28/2026 | LACDHS APPROVED |
Contact Information
| Contractor | Breeding Contracting Llc; Lic. No.: 1096003-B | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 5/4/2026 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 5/5/2026 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 5/11/2026 | Partial Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 5/11/2026 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 5/11/2026 | Not Ready for Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 5/15/2026 | Partial Approval | SEAN GRIFFITH |
| Footing/Foundation/Slab | 5/15/2026 | Partial Approval | SEAN GRIFFITH |
| Drywall Nailing | 5/28/2026 | Partial Approval | SEAN GRIFFITH |
| T-Bar Ceiling | 6/1/2026 | Partial Approval | SEAN GRIFFITH |
| Light Gage Steel Frame | 6/27/2026 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 6/27/2026 | Partial Approval | SEAN GRIFFITH |
| T-Bar Ceiling | 6/27/2026 | Off-Hour Fees Due | |
| T-Bar Ceiling | 6/27/2026 | Partial Approval | SEAN GRIFFITH |