2110 S MANSFIELD AVE 90016
Certificate Information: 2110 S MANSFIELD AVE 90016
- Application / Permit
- 25016-10000-37554
- Plan Check / Job No.
- B25LA54192
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: Garage conversion to ADU w/addition per LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
- Permit Issued
- Issued on 3/11/2026
- Issuing Office
- Current Status
- Issued on 3/11/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2025 | DAVID CASTILLO |
| Corrections Issued | 1/1/2026 | DAVID CASTILLO |
| Applicant returned to address corrections | 2/25/2026 | AMY GUEVARRA |
| Plan Check Approved | 3/10/2026 | AMY GUEVARRA |
| Issued | 3/11/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/16/2026 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 1/16/2026 | BIAINA HARITUNIAN |
| Address approval | Cleared | 1/21/2026 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2026 | DERRICK MAGEE |
| Construction near power lines | Cleared | 2/28/2026 | NAOMI GARCIA |
Contact Information
| Contractor | Vision Adu Llc; Lic. No.: 1115842-B | , |
| Engineer | Mahbub,, Muqtasid; Lic. No.: C97964 | 3115 BOULDER ST LOS ANGELES, CA 90063 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Interior/Exterior Lathing | 6/8/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/2/2026 | Partial Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 4/2/2026 | Partial Approval | JUSTIN HAWLEY |
| Special/Order Compliance | 4/2/2026 | Corrections Issued | JUSTIN HAWLEY |
| Sewer | 4/15/2026 | Approved | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 4/20/2026 | Corrections Issued | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 4/23/2026 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 4/23/2026 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 5/14/2026 | Not Ready for Inspection | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 5/14/2026 | Approved | JUSTIN HAWLEY |
| Deputy Wood Construction | 5/15/2026 | Conditional Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 5/19/2026 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2026 | Partial Approval | WILLIAM SIERRA |
| Green Building Rough | 5/19/2026 | Approved | WILLIAM SIERRA |