515 S FLOWER ST 50th Floor 90071

Certificate Information: 515 S FLOWER ST 50th Floor 90071

Application / Permit
25016-10000-37323
Plan Check / Job No.
B25LA53765
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office business or professional
Work Description
Ch1A - ePlan: INTERIOR TENANT IMPROVEMENT OF 23,665 SF OFFICE SPACE ON THE 50TH FLOOR OF AN EXISTING HIGH RISE BUILDING. NEW NON LOAD BEARING PARTITIONS, CEILINGS, MILLWORK, AND FINISHES. NEW RAISED FLOOR SYSTEM AND MOVABLE PARITIONS ANCHORED TO EXISTING BUILDING STRUCTURE.
Permit Issued
Issued on 5/5/2026
Issuing Office
Current Status
Issued on 5/5/2026

Permit Application Status History

Submitted 12/23/2025 APPLICANT
Assigned to Plan Check Engineer 12/30/2025 ARSALAN SHABESTARI
Assigned to Zoning Architect 1/2/2026 BENNY WONG
Corrections Issued 1/13/2026 ARSALAN SHABESTARI
Quality Review Completed 1/19/2026 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/30/2026 ARSALAN SHABESTARI
Plan Check Approved 5/4/2026 ARSALAN SHABESTARI
Issued 5/5/2026 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 1/26/2026 ROSALINDA MEZA
Miscellaneous Cleared 1/26/2026 ROSALINDA MEZA
Miscellaneous Cleared 1/26/2026 ROSALINDA MEZA
Miscellaneous Cleared 1/26/2026 ROSALINDA MEZA
Miscellaneous Cleared 1/26/2026 ROSALINDA MEZA
Green Code Cleared 2/27/2026 MICHAEL AYERS
Zoning Plan Check Cleared 3/10/2026 BENNY WONG
DAS Clearance Cleared 3/30/2026 Ricardo Ramirez Solis
Fire Marshal Fire Life Safety Cleared 4/29/2026 FIRE DEPARTMENT

Contact Information

Architect Kelley,, Brent Allen; Lic. No.: NA29540       ,
Contractor Bcci Construction Llc; Lic. No.: 492944-B 301 HOWARD ST SUITE 200      SAN FRANCISCO, CA 94105

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 5/22/2026 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 5/29/2026 Partial Approval PAUL BAZERKANIAN
Insulation 5/29/2026 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 6/1/2026 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 6/8/2026 Partial Approval PAUL BAZERKANIAN
Insulation 6/8/2026 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 6/16/2026 Approved PAUL BAZERKANIAN
Light Gage Steel Frame 6/18/2026 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 6/22/2026 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 6/26/2026 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 7/7/2026 Partial Approval PAUL BAZERKANIAN