607 S HIGHLAND AVE 90036
Certificate Information: 607 S HIGHLAND AVE 90036
- Application / Permit
- 25016-10000-37133
- Plan Check / Job No.
- B25LA53417
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: COMPLY WITH DEPARTMENT ORDER effective date 01/29/2026. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE Convert detached garage and storage to a detached ADU per state law (GC 66323(a)(1))
- Permit Issued
- Issued on 2/25/2026
- Issuing Office
- Current Status
- Issued on 2/25/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/4/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2026 | JOSE VELAZQUEZ |
| Corrections Issued | 1/8/2026 | JOSE VELAZQUEZ |
| Plan Check Approved | 2/24/2026 | DANIEL SMILEY |
| Issued | 2/25/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2026 | CELINA MORENO |
| Sewer availability | Cleared | 1/14/2026 | CELINA MORENO |
| CPC | Cleared | 1/16/2026 | JASON CHAN |
| CPC | Cleared | 1/16/2026 | JASON CHAN |
| Construction near power lines | Cleared | 2/18/2026 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2026 | XOCHITL ARQUIETA |
Contact Information
| Contractor | Harding Group Llc; Lic. No.: 1111934-B | , |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/27/2026 | Approved | PETER RUBIO |
| Footing/Foundation/Slab | 3/6/2026 | Not Ready for Inspection | PETER RUBIO |
| Excavation/Setback/Form/Re-Bar | 4/6/2026 | Partial Approval | PETER RUBIO |
| Footing/Foundation/Slab | 4/6/2026 | Partial Approval | PETER RUBIO |
| Underground Mechanical | 4/6/2026 | Approved | PETER RUBIO |
| Footing/Foundation/Slab | 4/15/2026 | Conditional Approval | PETER RUBIO |
| Deputy Drilled-In Anchors | 4/17/2026 | Conditional Approval | PETER RUBIO |
| BUILDING-Rough-Frame | 5/5/2026 | Not Ready for Inspection | PETER RUBIO |
| Green Building Rough | 5/5/2026 | Not Ready for Inspection | PETER RUBIO |
| METHANE-Rough | 5/5/2026 | Approved | PETER RUBIO |
| BUILDING-Rough-Frame | 5/28/2026 | Approved | PETER RUBIO |
| ELECTRICAL-Rough | 5/28/2026 | Approved | PETER RUBIO |
| Green Building Rough | 5/28/2026 | Approved | PETER RUBIO |
| HVAC-Rough | 5/28/2026 | Approved | PETER RUBIO |
| PLUMBING-Rough | 5/28/2026 | Approved | PETER RUBIO |