237 1/2 E 102ND ST 90003
Certificate Information: 237 1/2 E 102ND ST 90003
- Application / Permit
- 25016-10000-36219
- Plan Check / Job No.
- B25LA52002
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert detached garage to ADU per state GC 66323(a)(4). NFPA-13D fire sprinklers throughout.
- Permit Issued
- Issued on 4/10/2026
- Issuing Office
- Current Status
- Issued on 4/10/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2025 | SHANGQIN XIE |
| Corrections Issued | 12/17/2025 | SHANGQIN XIE |
| Applicant returned to address corrections | 4/2/2026 | DANIEL SMILEY |
| Plan Check Approved | 4/8/2026 | DANIEL SANJUAN |
| Issued | 4/10/2026 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/10/2026 | RIDWAN HARDY |
| Address approval | Cleared | 3/19/2026 | LESLIE PEREZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2026 | LESLIE PEREZ |
| Sewer availability | Cleared | 3/24/2026 | TONY CHIANG |
Contact Information
| Contractor | Yor Construction And Investments Inc; Lic. No.: 978430-B | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/22/2026 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 4/27/2026 | Corrections Issued | BEN MOLSTAD |
| Underground Mechanical | 4/27/2026 | Partial Approval | BEN MOLSTAD |
| Deputy Drilled-In Anchors | 4/28/2026 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 4/28/2026 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2026 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 6/2/2026 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2026 | Partial Approval | BEN MOLSTAD |
| HVAC-Rough | 6/2/2026 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 6/2/2026 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 6/5/2026 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 6/5/2026 | Approved | BEN MOLSTAD |
| HVAC-Rough | 6/5/2026 | Approved | BEN MOLSTAD |