1733 N ROSCOMARE ROAD 90077

Certificate Information: 1733 N ROSCOMARE ROAD 90077

Application / Permit
25016-10000-35723
Plan Check / Job No.
B25LA51288
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Addition to and convert (E) detached garage to ADU 600 sq.ft . Per LAMC 12.22 A.33(b)(1) 3
Permit Issued
Issued on 2/4/2026
Issuing Office
Current Status
Issued on 2/4/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/15/2025 APPLICANT
Assigned to Plan Check Engineer 12/18/2025 ALFREDO JARA
Corrections Issued 1/12/2026 JOHNPAUL ISIP
Plan Check Approved 1/21/2026 KAVIAN REFAHI
Issued 2/4/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/30/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 12/30/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 12/30/2025 MICHAEL BROWN
Sewer availability Cleared 12/30/2025 MICHAEL BROWN
Miscellaneous Cleared 12/31/2025 MICHAEL BROWN
Grading Pre-Inspection Cleared 1/8/2026 MICHAEL TEMPLE

Contact Information

Contractor H I C Builders Inc; Lic. No.: 1078180-B       ,
Contractor Hic Builders Inc; Lic. No.: 1078180-B       ,

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/12/2026 Corrections Issued EVAN COOPER
Excavation/Setback/Form/Re-Bar 2/25/2026 Partial Approval EVAN COOPER
Deputy Drilled-In Anchors 3/2/2026 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 3/3/2026 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 3/3/2026 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 4/23/2026 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/23/2026 Partial Approval CARLOS MATAMOROS
HVAC-Rough 4/23/2026 Approved CARLOS MATAMOROS
PLUMBING-Rough 4/23/2026 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 4/29/2026 Approved RYAN SALAZAR
Underground Mechanical 5/5/2026 Approved CARLOS MATAMOROS
Gas Test 5/6/2026 Corrections Issued EVAN COOPER
Underground Mechanical 5/6/2026 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 5/20/2026 Partial Approval EVAN COOPER
Green Building Rough 5/20/2026 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 5/27/2026 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 5/28/2026 Approved EVAN COOPER
Green Building Rough 5/28/2026 Approved EVAN COOPER
Insulation 5/28/2026 Approved EVAN COOPER
Interior/Exterior Lathing 5/28/2026 Partial Approval EVAN COOPER
Drywall Nailing 6/2/2026 Approved DAVID SCANTLIN