15955 W LONDELIUS ST 91343

Certificate Information: 15955 W LONDELIUS ST 91343

Application / Permit
25016-10000-35702
Plan Check / Job No.
B25LA51263
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMODEL OF EXISTING SINGLE FAMILY DWELLING TO CONVERT ATTACHED WORKSHOP TO LIVING SPACE AND CONVERT ATTACHED GARAGE TO NEW ATTACHED ADU PER GC 66323(a)(1)
Permit Issued
Issued on 12/24/2025
Issuing Office
Metro
Current Status
CofO Issued on 6/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2025 APPLICANT
Assigned to Plan Check Engineer 12/10/2025 ADAM HEGAZI
Corrections Issued 12/11/2025 ADAM HEGAZI
Building Plans Picked Up 12/16/2025 APPLICANT
Plan Check Approved 12/18/2025 SUNMIN LEE
Issued 12/24/2025 APPLICANT
CofO in Progress 6/10/2026 RAUL OLAGI
Permit Finaled 6/23/2026 RUBEN SALAS
CofO Issued 6/23/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/12/2025 BIAINA HARITUNIAN
Sewer availability Cleared 12/12/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/16/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Jad; Lic. No.: C96371 1149 S BROADWAY   6TH FLOOR    LOS ANGELES, CA 90015

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/5/2026 Partial Inspection GAREN HAYRAPETYAN
Sewer 1/5/2026 Approved GAREN HAYRAPETYAN
Deputy Drilled-In Anchors 1/7/2026 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/7/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 1/7/2026 Partial Approval GAREN HAYRAPETYAN
Special/Order Compliance 1/7/2026 Approved GAREN HAYRAPETYAN
Special/Order Compliance 1/29/2026 Corrections Issued GAREN HAYRAPETYAN
Underground Mechanical 1/29/2026 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 1/30/2026 Partial Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 1/30/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Rough 1/30/2026 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 1/30/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 1/30/2026 Approved GAREN HAYRAPETYAN
Service/Power Release 1/30/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Underground Mechanical 1/30/2026 Approved GAREN HAYRAPETYAN
Wood Frame 1/30/2026 Partial Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 2/4/2026 Approved GAREN HAYRAPETYAN
Insulation 2/4/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 2/4/2026 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 2/6/2026 Approved GAREN HAYRAPETYAN
Green Building Rough 2/6/2026 Approved GAREN HAYRAPETYAN
Drywall Nailing 2/10/2026 Approved MICHAEL CORTEZ
Shower Pan 2/10/2026 Corrections Issued MICHAEL CORTEZ
Shower Pan 2/12/2026 No Access for Inspection MICHAEL CORTEZ
Shower Pan 2/17/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 2/24/2026 Approved MICHAEL CORTEZ
ELECTRICAL-Final 3/23/2026 Corrections Issued KIRK SANDERS
Final 3/23/2026 Corrections Issued KIRK SANDERS
Green Building Final 3/23/2026 Not Ready for Inspection KIRK SANDERS
HVAC-Final 3/23/2026 Corrections Issued KIRK SANDERS
PLUMBING-Final 3/23/2026 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/23/2026 SGSOV Approved KIRK SANDERS
Service/Power Release 3/23/2026 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 3/23/2026 Corrections Issued KIRK SANDERS
Final 3/31/2026 OK to Issue CofO KIRK SANDERS
Green Building Final 3/31/2026 Approved KIRK SANDERS
Service/Power Release 3/31/2026 Approved KIRK SANDERS
Smoke Detectors 3/31/2026 Approved KIRK SANDERS
Special/Order Compliance 3/31/2026 Approved KIRK SANDERS