1847 N FANNING ST 90026
Certificate Information: 1847 N FANNING ST 90026
- Application / Permit
- 25016-10000-35570
- Plan Check / Job No.
- B25LA51028
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan Replace and extend existing Open deck at first floor per Engineer design and soil report.
- Permit Issued
- Issued on 1/13/2026
- Issuing Office
- Current Status
- Permit Finaled on 5/28/2026
Permit Application Status History
| Submitted | 12/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2025 | KHUONG TRUONG |
| Assigned to Zoning Architect | 12/11/2025 | LY CHEA |
| Corrections Issued | 12/13/2025 | KHUONG TRUONG |
| Quality Review Completed | 12/18/2025 | GARO TELMI |
| Applicant returned to address corrections | 1/6/2026 | KHUONG TRUONG |
| Plan Check Approved | 1/12/2026 | KHUONG TRUONG |
| Issued | 1/13/2026 | APPLICANT |
| Permit Finaled | 5/27/2026 | HAMIK HARTOUNIAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/11/2025 | KHUONG TRUONG |
| Zoning Plan Check | Cleared | 1/5/2026 | LY CHEA |
Contact Information
| Architect | Perella,, Ryan Adam; Lic. No.: NA30833 | , |
| Contractor | Owner-Builder | , |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Sayah,, Daniel H; Lic. No.: NA67905 | , |
| Geologist | Irvine,, Jon Alan; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/25/2026 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 3/2/2026 | Partial Approval | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 3/2/2026 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 3/9/2026 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 3/18/2026 | Conditional Approval | GEM DE OCAMPO |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2026 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/6/2026 | Approved | GEM DE OCAMPO |
| Final | 5/19/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/19/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 5/27/2026 | Permit Finaled | HAMIK HARTOUNIAN |