1651 S WILTON PL 90019
Certificate Information: 1651 S WILTON PL 90019
- Application / Permit
- 25016-10000-35123
- Plan Check / Job No.
- B25LA50296
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN . MAJOR REMODEL TO REPLACE EXISTING WOOD STUD WALLS DUE TO DRY-ROT AS NECESSARY. TWO NEW BATHROOMS, NEW WINDOWS & DOORS. REMODEL KITCHEN AND THREE BEDROOMS.
- Permit Issued
- Issued on 4/2/2026
- Issuing Office
- Current Status
- Issued on 4/2/2026
Permit Application Status History
| Submitted | 12/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2025 | ARSALAN SHABESTARI |
| Assigned to Zoning Architect | 12/4/2025 | MELISSA QUINONES |
| Corrections Issued | 12/15/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 12/24/2025 | GARO TELMI |
| Applicant returned to address corrections | 3/7/2026 | ARSALAN SHABESTARI |
| Plan Check Approved | 4/1/2026 | ARSALAN SHABESTARI |
| Issued | 4/2/2026 | APPLICANT |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 2/12/2026 | LAMBERT GIESSINGER |
| Community Plan Implem. Overlay | Cleared | 3/10/2026 | JOSE CARDENAS |
| Zoning Plan Check | Cleared | 3/23/2026 | Cristina Salazar |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Wood Frame | 6/8/2026 |
| Rough-Elec/Plmb/HVAC | 6/8/2026 |
| Insulation | 6/8/2026 |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2026 | Partial Approval | WILLIAM MICHALAK |
| Notice of Violation | 4/9/2026 | Not Required | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 4/15/2026 | Corrections Issued | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2026 | Corrections Issued | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 5/1/2026 | Corrections Issued | WILLIAM MICHALAK |
| Pre-Inspection | 5/19/2026 | Corrections Issued | WILLIAM MICHALAK |
| Deputy Drilled-In Anchors | 5/29/2026 | Corrections Issued | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 5/29/2026 | Partial Approval | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 5/29/2026 | Corrections Issued | WILLIAM MICHALAK |
| Shower Pan | 5/29/2026 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 6/2/2026 | Not Ready for Inspection | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2026 | Approved | WILLIAM MICHALAK |
| Gas Test | 6/2/2026 | Not Ready for Inspection | WILLIAM MICHALAK |
| Rough-Elec/Plmb/HVAC | 6/2/2026 | Partial Approval | WILLIAM MICHALAK |
| Wood Frame | 6/2/2026 | Partial Approval | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 6/3/2026 | Corrections Issued | WILLIAM MICHALAK |
| Gas Test | 6/3/2026 | Not Ready for Inspection | WILLIAM MICHALAK |
| PLUMBING-Rough | 6/3/2026 | Corrections Issued | WILLIAM MICHALAK |