2156 1/2 S PATRICIA AVE 90025

Certificate Information: 2156 1/2 S PATRICIA AVE 90025

Application / Permit
25016-10000-35040
Plan Check / Job No.
B25LA50157
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Detached 1-story garage conversion to ADU per LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 12/24/2025
Issuing Office
Current Status
CofO Issued on 5/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2025 APPLICANT
Assigned to Plan Check Engineer 12/3/2025 DAVID CASTILLO
Corrections Issued 12/4/2025 DAVID CASTILLO
Applicant returned to address corrections 12/18/2025 AMY GUEVARRA
Plan Check Approved 12/24/2025 AMY GUEVARRA
Issued 12/24/2025 APPLICANT
CofO in Progress 5/15/2026 DAVID SCANTLIN
Permit Finaled 5/15/2026 RICHARD STEINBACH
CofO Issued 5/15/2026 RICHARD STEINBACH
Permit Finaled 5/15/2026 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/9/2025 GERMAN RODRIGUEZ MENDOZA
Address approval Cleared 12/17/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 12/17/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 12/17/2025 MICHAEL BROWN
Sewer availability Cleared 12/17/2025 MICHAEL BROWN
Specific Plan Cleared 12/19/2025 EDER ROMERO

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/12/2026 Partial Inspection DANIEL VERA
Footing/Foundation/Slab 1/20/2026 Approved EVAN COOPER
PLUMBING-Rough 2/3/2026 Conditional Approval RYAN SALAZAR
BUILDING-Rough-Frame 2/4/2026 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 2/4/2026 Approved RYAN SALAZAR
METHANE-Rough 2/4/2026 Approved RYAN SALAZAR
BUILDING-Rough-Frame 2/11/2026 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 2/11/2026 Corrections Issued CARLOS MATAMOROS
Gas Test 2/13/2026 Approved CARLOS MATAMOROS
Sewer 2/13/2026 Approved CARLOS MATAMOROS
Underground Mechanical 2/13/2026 Approved CARLOS MATAMOROS
PLUMBING-Rough 2/17/2026 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 2/24/2026 Conditional Approval EVAN COOPER
HVAC-Rough 2/24/2026 Approved EVAN COOPER
Insulation 2/24/2026 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 2/27/2026 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 3/16/2026 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/20/2026 Approved CARLOS MATAMOROS
PLUMBING-Rough 3/20/2026 Approved CARLOS MATAMOROS
Drywall Nailing 4/2/2026 Approved RYAN SALAZAR
Shower Pan 4/2/2026 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/8/2026 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 5/6/2026 Corrections Issued RYAN SALAZAR
HVAC-Final 5/6/2026 Corrections Issued RYAN SALAZAR
Final 5/14/2026 OK to Issue CofO DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 5/14/2026 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 5/14/2026 Approved DAVID SCANTLIN