1173 S CARMONA AVE 90019
Certificate Information: 1173 S CARMONA AVE 90019
- Application / Permit
- 25016-10000-34434
- Plan Check / Job No.
- B25LA49293
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert (E) Detached Garage/Storage Room into an Accessory Dwelling Unit per GC 66323(a)(1)
- Permit Issued
- Issued on 1/29/2026
- Issuing Office
- Current Status
- Issued on 1/29/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2025 | AMY GUEVARRA |
| Corrections Issued | 12/3/2025 | AMY GUEVARRA |
| Plan Check Approved | 1/29/2026 | REZA HAGHIGHAT |
| Issued | 1/29/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/23/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/23/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2026 | CARLOS AGUILERA |
Contact Information
| Architect | Abernathy,, Dean Lowell; Lic. No.: C23030 | 1107 VALLEY CIRCLE COSTA MESA, CA 92627 |
| Contractor | J O Construction; Lic. No.: 1057456-B | , |
| Engineer | Jamil,, Bashar S; Lic. No.: C83129 | 751 SHASTA DR CORONA, CA 92881 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/4/2026 | Partial Approval | WILLIAM SIERRA |
| Underground Mechanical | 3/4/2026 | Partial Approval | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 3/6/2026 | Corrections Issued | WILLIAM SIERRA |
| Footing/Foundation/Slab | 3/6/2026 | Corrections Issued | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 3/10/2026 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 3/10/2026 | Corrections Issued | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 3/13/2026 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 3/13/2026 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/9/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Rough | 4/9/2026 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Rough | 4/9/2026 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 4/9/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Sewer | 4/9/2026 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 4/15/2026 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Rough | 4/15/2026 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 4/15/2026 | Corrections Issued | BRENDAN MORELLI |
| Underground Mechanical | 4/15/2026 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/20/2026 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Rough | 4/20/2026 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 4/20/2026 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 4/20/2026 | Partial Approval | WILLIAM SIERRA |
| METHANE-Rough | 4/20/2026 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 4/20/2026 | Approved | WILLIAM SIERRA |
| Insulation | 4/23/2026 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 4/28/2026 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/19/2026 | Approved | DAVID WILLIAMS |