1112 E 102ND ST 90002
Certificate Information: 1112 E 102ND ST 90002
- Application / Permit
- 25016-10000-33659
- Plan Check / Job No.
- B25LA48022
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 18'-0"X20'-0" GARAGE INTO NEW ADU PER STATE LAW
- Permit Issued
- Issued on 12/17/2025
- Issuing Office
- Current Status
- CofO Corrected on 5/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2025 | SUNMIN LEE |
| Corrections Issued | 11/21/2025 | SUNMIN LEE |
| Applicant returned to address corrections | 12/10/2025 | SUNMIN LEE |
| Plan Check Approved | 12/16/2025 | SUNMIN LEE |
| Issued | 12/17/2025 | APPLICANT |
| CofO in Progress | 5/13/2026 | ARTHUR NEGRETE |
| Permit Finaled-Status Void | 5/13/2026 | ANSON MAGLASANG |
| CofO Issued-Status Void | 5/13/2026 | ANSON MAGLASANG |
| Re-Activate Permit | 5/21/2026 | ANSON MAGLASANG |
| Permit Finaled | 5/21/2026 | ANSON MAGLASANG |
| CofO Corrected | 5/21/2026 | ANSON MAGLASANG |
| Permit Finaled | 5/21/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 11/24/2025 | DIANA RENTERIA |
| Roof/Waste drainage to street | Cleared | 11/24/2025 | DIANA RENTERIA |
| Sewer availability | Cleared | 11/24/2025 | DIANA RENTERIA |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2025 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
| Engineer | Zhong,, Raymond; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/23/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 1/23/2026 | Approved | ARTHUR NEGRETE |
| Sewer | 1/23/2026 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 4/17/2026 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 4/17/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 4/17/2026 | Approved | ARTHUR NEGRETE |
| Final | 4/17/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 4/17/2026 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 4/17/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 4/17/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 4/17/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 4/17/2026 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 4/17/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 4/17/2026 | Approved | ARTHUR NEGRETE |
| Final | 5/7/2026 | Partial Inspection | ARTHUR NEGRETE |