2034 S CORNING ST 90034

Certificate Information: 2034 S CORNING ST 90034

Application / Permit
25016-10000-33495
Plan Check / Job No.
B25LA47667
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: RETROFIT SOFT STORY CONDITION OF AN EXISTING 2 STORY 6 UNITS APARTMENT BY REMOVING (E) COLUMN AND REPLACING BY (N) 2-WAY HSS COL 9x9x5/8 COL IN EAST ELEVATION PER 2023 CBC AND CITY OF LOS ANGELES SOFT-STORY RETROFIT ORDINANCE
Permit Issued
Issued on 12/18/2025
Issuing Office
Current Status
CofC Issued on 4/15/2026

Permit Application Status History

Submitted 11/13/2025 APPLICANT
Assigned to Plan Check Engineer 11/13/2025 HANS SANTIAGO
Corrections Issued 11/17/2025 HANS SANTIAGO
Quality Review Completed 11/17/2025 CHARLES CHANG
Applicant returned to address corrections 11/23/2025 HANS SANTIAGO
Plan Check Approved 12/3/2025 ANDREW SANTIAGO
Issued 12/18/2025 APPLICANT
OK for CofC 4/14/2026 FARHAD DADBIN
CofC Issued 4/15/2026 VASIL MIHALEV

Permit Application Clearance Information

Tenant Habitability Plan Cleared 12/18/2025 ARIC DEFUSCO

Contact Information

Contractor Shaolian Sol K And Assoc Inc; Lic. No.: 720390-B       ,
Contractor Sks Construction; Lic. No.: 720390-B       ,
Engineer Shaolian,, Shahab Joseph; Lic. No.: C84155 15134 FRIAR ST      VAN NUYS, CA 91411

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/5/2026 No Access for Inspection DANIEL VARNUM
Pre-Inspection 2/11/2026 Approved FARHAD DADBIN
Deputy Reinf. Concrete 3/11/2026 Partial Approval VASIL MIHALEV
Footing/Foundation/Slab 3/17/2026 Approved DANIEL VARNUM
Wood Frame 3/17/2026 Approved DANIEL VARNUM
Deputy Steel/Welding 4/1/2026 Conditional Approval FARHAD DADBIN
Interior/Exterior Lathing 4/1/2026 Approved FARHAD DADBIN
Final 4/10/2026 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 4/10/2026 SGSOV Approved FARHAD DADBIN
Smoke Detectors 4/10/2026 Not Ready for Inspection FARHAD DADBIN
Final 4/14/2026 OK for CofC FARHAD DADBIN
Smoke Detectors 4/14/2026 Approved FARHAD DADBIN