2034 S CORNING ST 90034
Certificate Information: 2034 S CORNING ST 90034
- Application / Permit
- 25016-10000-33495
- Plan Check / Job No.
- B25LA47667
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: RETROFIT SOFT STORY CONDITION OF AN EXISTING 2 STORY 6 UNITS APARTMENT BY REMOVING (E) COLUMN AND REPLACING BY (N) 2-WAY HSS COL 9x9x5/8 COL IN EAST ELEVATION PER 2023 CBC AND CITY OF LOS ANGELES SOFT-STORY RETROFIT ORDINANCE
- Permit Issued
- Issued on 12/18/2025
- Issuing Office
- Current Status
- CofC Issued on 4/15/2026
Permit Application Status History
| Submitted | 11/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2025 | HANS SANTIAGO |
| Corrections Issued | 11/17/2025 | HANS SANTIAGO |
| Quality Review Completed | 11/17/2025 | CHARLES CHANG |
| Applicant returned to address corrections | 11/23/2025 | HANS SANTIAGO |
| Plan Check Approved | 12/3/2025 | ANDREW SANTIAGO |
| Issued | 12/18/2025 | APPLICANT |
| OK for CofC | 4/14/2026 | FARHAD DADBIN |
| CofC Issued | 4/15/2026 | VASIL MIHALEV |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 12/18/2025 | ARIC DEFUSCO |
Contact Information
| Contractor | Shaolian Sol K And Assoc Inc; Lic. No.: 720390-B | , |
| Contractor | Sks Construction; Lic. No.: 720390-B | , |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 15134 FRIAR ST VAN NUYS, CA 91411 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/5/2026 | No Access for Inspection | DANIEL VARNUM |
| Pre-Inspection | 2/11/2026 | Approved | FARHAD DADBIN |
| Deputy Reinf. Concrete | 3/11/2026 | Partial Approval | VASIL MIHALEV |
| Footing/Foundation/Slab | 3/17/2026 | Approved | DANIEL VARNUM |
| Wood Frame | 3/17/2026 | Approved | DANIEL VARNUM |
| Deputy Steel/Welding | 4/1/2026 | Conditional Approval | FARHAD DADBIN |
| Interior/Exterior Lathing | 4/1/2026 | Approved | FARHAD DADBIN |
| Final | 4/10/2026 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2026 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 4/10/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 4/14/2026 | OK for CofC | FARHAD DADBIN |
| Smoke Detectors | 4/14/2026 | Approved | FARHAD DADBIN |