1994 W JEFFERSON BLVD 90018
Certificate Information: 1994 W JEFFERSON BLVD 90018
- Application / Permit
- 25016-10000-33452
- Plan Check / Job No.
- B25LA47535
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Auditorium (3000 seats max)
- Work Description
- EPLAN. Change of use from a Retail/Glass store to Auditorium (for meetings)
- Permit Issued
- Issued on 2/20/2026
- Issuing Office
- Current Status
- Issued on 2/20/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2025 | PRANITA SHAH |
| Assigned to Zoning Architect | 11/13/2025 | KRISTEL MARQUEZ |
| Corrections Issued | 11/18/2025 | PRANITA SHAH |
| Quality Review Completed | 11/24/2025 | GARO TELMI |
| Plan Check Approved | 2/10/2026 | PRANITA SHAH |
| Issued | 2/20/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/19/2025 | CARLOS AGUILERA |
| HPOZ | Cleared | 1/14/2026 | DANIEL MATA |
| Community Plan Implem. Overlay | Cleared | 1/20/2026 | MANERI ROMAN |
| DAS Clearance | Cleared | 1/20/2026 | ELIZABETH TOMS |
| Zoning Plan Check | Cleared | 1/20/2026 | KRISTEL MARQUEZ |
Contact Information
| Architect | Flitsch,, Thomas Jacob; Lic. No.: NA25422 | , |
| Contractor | Jcs General Construction Inc; Lic. No.: 1045869-B | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/24/2026 | Partial Inspection | JEROME BLACKWOOD |
| Deputy Drilled-In Anchors | 3/16/2026 | Partial Approval | PAUL BAZERKANIAN |
| Excavation/Setback/Form/Re-Bar | 3/17/2026 | Corrections Issued | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 3/20/2026 | Partial Approval | PAUL BAZERKANIAN |
| Excavation/Setback/Form/Re-Bar | 4/7/2026 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Rough | 4/7/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 4/7/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Deputy Drilled-In Anchors | 5/8/2026 | Partial Approval | PAUL BAZERKANIAN |
| Excavation/Setback/Form/Re-Bar | 5/11/2026 | Partial Approval | ALFREDO LOPEZ |
| METHANE-Rough | 5/11/2026 | Approved | ALFREDO LOPEZ |
| Wood Frame | 5/11/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 5/15/2026 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 5/20/2026 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 5/26/2026 | Approved | ALFREDO LOPEZ |