444 S CITRUS AVE 90036

Certificate Information: 444 S CITRUS AVE 90036

Application / Permit
25016-10000-33429
Plan Check / Job No.
B25LA47522
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN REMODEL KITCHEN, REPLACE DAMAGED EXTERIOR WALL, ADD A RIDGE BEAM AND NEW CEILING JOISTS . ADD 3' OVERHANG AT REAR OF (E) SFD
Permit Issued
Issued on 11/25/2025
Issuing Office
Current Status
Permit Finaled on 2/27/2026

Permit Application Status History

Submitted 11/11/2025 APPLICANT
Assigned to Plan Check Engineer 11/12/2025 MINA HABILI
Corrections Issued 11/12/2025 MINA HABILI
Applicant returned to address corrections 11/20/2025 MINA HABILI
Plan Check Approved 11/24/2025 MINA HABILI
Issued 11/25/2025 APPLICANT
Permit Finaled 2/26/2026 ALEX COLIN

Permit Application Clearance Information

CPC Cleared 11/19/2025 ROSALINDA MEZA
Roof/Waste drainage to street Cleared 11/19/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 11/20/2025 CINDY QI

Contact Information

Architect Hanna,, Remon; Lic. No.: NA36271       ,
Contractor Owner-Builder       ,
Engineer Abdel, Messih, Raymond; Lic. No.: NA79913       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/5/2025 Corrections Issued RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 Not Ready for Inspection RONNIE MINDANAO
Footing/Foundation/Slab 12/5/2025 Approved RONNIE MINDANAO
Interior/Exterior Lathing 12/5/2025 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 12/8/2025 Approved RONNIE MINDANAO
Footing/Foundation/Slab 12/8/2025 Approved RONNIE MINDANAO
HVAC-Rough 12/8/2025 Corrections Issued RONNIE MINDANAO
PLUMBING-Rough 12/8/2025 Approved RONNIE MINDANAO
Wood Frame 12/8/2025 Corrections Issued RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Not Ready for Inspection RONNIE MINDANAO
Wood Frame 12/10/2025 Partial Approval RONNIE MINDANAO
Deputy Wood Construction 12/16/2025 Conditional Approval ALEX COLIN
Drywall Nailing 12/17/2025 Partial Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Partial Approval RONNIE MINDANAO
Drywall Nailing 12/19/2025 Approved RONNIE MINDANAO
Gas Test 12/23/2025 Approved RONNIE MINDANAO
Final 2/26/2026 Permit Finaled ALEX COLIN
SGSOV-Seismic Gas S/O Valve 2/26/2026 SGSOV Approved ALEX COLIN
Smoke Detectors 2/26/2026 Approved ALEX COLIN