515 S FLOWER ST 46TH FLOOR 90071
Certificate Information: 515 S FLOWER ST 46TH FLOOR 90071
- Application / Permit
- 25016-10000-33200
- Plan Check / Job No.
- B25LA47046
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office business or professional
- Work Description
- OFFICE TENANT IMPROVEMENT. WORK TO INCLUDE NON-LOAD BEARING WALLS, CEILING, DOORS, FIXTURES, FINISHES, MILLWORK. NO STRUCTURAL SCOPE. 46TH FLOOR.
- Permit Issued
- Issued on 1/29/2026
- Issuing Office
- Metro
- Current Status
- Issued on 1/29/2026
Permit Application Status History
| Submitted | 11/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2025 | DANIEL SANJUAN |
| Corrections Issued | 11/13/2025 | DANIEL SANJUAN |
| Building Plans Picked Up | 11/25/2025 | APPLICANT |
| Plan Check Approved | 1/16/2026 | DANIEL YIP |
| Issued | 1/29/2026 | APPLICANT |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 1/13/2026 | SARAH ZHANG |
Contact Information
| Architect | Causseaux,, Stephen R; Lic. No.: C29179 | 4408 S ROTTERDAM DR BLOOMINGTON, IN 47401 |
| Contractor | Corporate Contractors Inc; Lic. No.: 604407-B | 2550 CORPORATE PLACE STE C111 MONTEREY PARK, CA 91754 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 7/24/2026 Time Frame: 9-11 |
| Smoke Detectors | 7/24/2026 Time Frame: 9-11 |
| SGSOV-Seismic Gas S/O Valve | 7/24/2026 Time Frame: 9-11 |
| Green Building Final | 7/24/2026 Time Frame: 9-11 |
Inspection Request History
| Light Gage Steel Frame | 3/4/2026 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 3/6/2026 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 3/6/2026 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 3/25/2026 | Partial Approval | PAUL BAZERKANIAN |
| Deputy Steel/Welding | 4/1/2026 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 4/1/2026 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 4/13/2026 | Partial Approval | REGINA MENDEZ |
| Light Gage Steel Frame | 4/17/2026 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 4/21/2026 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 5/13/2026 | Partial Approval | REGINA MENDEZ |
| T-Bar Ceiling | 5/13/2026 | Partial Approval | REGINA MENDEZ |
| Drywall Nailing | 5/18/2026 | Approved | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 5/18/2026 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 5/20/2026 | Partial Inspection | PAUL BAZERKANIAN |
| Drywall Nailing | 5/21/2026 | Partial Approval | PAUL BAZERKANIAN |