4878 W FOUNTAIN AVE 90029
Certificate Information: 4878 W FOUNTAIN AVE 90029
- Application / Permit
- 25016-10000-32975
- Plan Check / Job No.
- B25LA46567
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Change of a portion a retail to restaurant and added it to the adjacent restaurant space to become one restaurant, new mechanical equipment snd 3 new skylighte.
- Permit Issued
- Issued on 3/3/2026
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2026 | SALVADOR QUINTANILLA |
| Plan Check Approved | 2/10/2026 | SALVADOR QUINTANILLA |
| Issued | 3/3/2026 | APPLICANT |
| CofO in Progress | 7/17/2026 | REGINA MENDEZ |
| Permit Finaled | 7/17/2026 | RAFAEL ESPINOZA |
| CofO Issued | 7/17/2026 | RAFAEL ESPINOZA |
| Permit Finaled | 7/17/2026 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Miscellaneous | Cleared | 11/18/2025 | ROSALINDA MEZA |
| "Q" conditions | Cleared | 11/21/2025 | ROSALINDA MEZA |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2025 | JESUS LUNA |
| Sewer availability | Cleared | 12/5/2025 | JESUS LUNA |
| Food Service Establishment | Cleared | 12/11/2025 | ANSON PUA |
| Miscellaneous | Cleared | 1/13/2026 | FIPE LEILUA |
| Food establishment approval | Cleared | 1/20/2026 | LACDHS APPROVED |
| Specific Plan | Cleared | 1/20/2026 | FIPE LEILUA |
| ZA Case | Cleared | 2/6/2026 | MATTHEW COMPANA |
Contact Information
| Contractor | J B C I; Lic. No.: 979172-B | 7732 TALBERT AVE UNIT C HUNTINGTON BEACH, CA 92648 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 3/31/2026 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 3/31/2026 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 4/7/2026 | Partial Approval | LUIS CCAMACHO |
| T-Bar Ceiling | 5/18/2026 | Conditional Approval | SEAN POMISH |
| Final | 7/13/2026 | Not Ready for Inspection | REGINA MENDEZ |
| SGSOV-Seismic Gas S/O Valve | 7/13/2026 | SGSOV Not Ready | REGINA MENDEZ |
| Smoke Detectors | 7/13/2026 | Not Ready for Inspection | REGINA MENDEZ |
| Final | 7/16/2026 | OK to Issue CofO | REGINA MENDEZ |
| SGSOV-Seismic Gas S/O Valve | 7/16/2026 | SGSOV Approved | REGINA MENDEZ |
| Smoke Detectors | 7/16/2026 | Approved | REGINA MENDEZ |