3167 W GARDEN AVE 90039
Certificate Information: 3167 W GARDEN AVE 90039
- Application / Permit
- 25016-10000-32499
- Plan Check / Job No.
- B25LA45854
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert (E) detached garage into ADU per GC 66323(a)(1). All work done per WFPP.
- Permit Issued
- Issued on 12/1/2025
- Issuing Office
- Current Status
- Issued on 12/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2025 | DAVID CASTILLO |
| Corrections Issued | 11/8/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/20/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/25/2025 | CAROLEAN BASMA |
| Plan Check Approved | 12/1/2025 | CAROLEAN BASMA |
| Issued | 12/1/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 11/17/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 11/17/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/24/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 12/24/2025 | Partial Approval | NICHOLAS LOPEZ |
| Deputy Drilled-In Anchors | 12/29/2025 | Conditional Approval | ALEX COLIN |
| Footing/Foundation/Slab | 12/31/2025 | Approved | NICHOLAS LOPEZ |
| Sewer | 1/20/2026 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2026 | Approved | NICHOLAS LOPEZ |
| Pre-Inspection | 1/28/2026 | Partial Inspection | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 2/10/2026 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 2/10/2026 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Rough | 2/10/2026 | Corrections Issued | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 2/18/2026 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 2/18/2026 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 2/18/2026 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 2/18/2026 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 2/18/2026 | Approved | NICHOLAS LOPEZ |
| Insulation | 2/24/2026 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 3/2/2026 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 3/26/2026 | Partial Approval | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 4/1/2026 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 4/21/2026 | Approved | GEM DE OCAMPO |
| ELECTRICAL-Rough | 4/22/2026 | Approved | NICHOLAS LOPEZ |