3167 W GARDEN AVE 90039

Certificate Information: 3167 W GARDEN AVE 90039

Application / Permit
25016-10000-32499
Plan Check / Job No.
B25LA45854
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) detached garage into ADU per GC 66323(a)(1). All work done per WFPP.
Permit Issued
Issued on 12/1/2025
Issuing Office
Current Status
Issued on 12/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/5/2025 APPLICANT
Assigned to Plan Check Engineer 11/7/2025 DAVID CASTILLO
Corrections Issued 11/8/2025 DAVID CASTILLO
Applicant returned to address corrections 11/20/2025 DAVID CASTILLO
Applicant returned to address corrections 11/25/2025 CAROLEAN BASMA
Plan Check Approved 12/1/2025 CAROLEAN BASMA
Issued 12/1/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/17/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 11/17/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 11/17/2025 MICHAEL BROWN
Sewer availability Cleared 11/17/2025 MICHAEL BROWN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/24/2025 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 12/24/2025 Partial Approval NICHOLAS LOPEZ
Deputy Drilled-In Anchors 12/29/2025 Conditional Approval ALEX COLIN
Footing/Foundation/Slab 12/31/2025 Approved NICHOLAS LOPEZ
Sewer 1/20/2026 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/28/2026 Approved NICHOLAS LOPEZ
Pre-Inspection 1/28/2026 Partial Inspection NICHOLAS LOPEZ
ELECTRICAL-Rough 2/10/2026 Approved NICHOLAS LOPEZ
HVAC-Rough 2/10/2026 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 2/10/2026 Corrections Issued NICHOLAS LOPEZ
BUILDING-Rough-Frame 2/18/2026 Approved NICHOLAS LOPEZ
Green Building Rough 2/18/2026 Approved NICHOLAS LOPEZ
HVAC-Rough 2/18/2026 Approved NICHOLAS LOPEZ
PLUMBING-Rough 2/18/2026 Approved NICHOLAS LOPEZ
Shower Pan 2/18/2026 Approved NICHOLAS LOPEZ
Insulation 2/24/2026 Approved NICHOLAS LOPEZ
Drywall Nailing 3/2/2026 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 3/26/2026 Partial Approval NICHOLAS LOPEZ
Interior/Exterior Lathing 4/1/2026 Approved NICHOLAS LOPEZ
Underground Mechanical 4/21/2026 Approved GEM DE OCAMPO
ELECTRICAL-Rough 4/22/2026 Approved NICHOLAS LOPEZ