11615 W DARLINGTON AVE 90049

Certificate Information: 11615 W DARLINGTON AVE 90049

Application / Permit
25016-10000-32228
Plan Check / Job No.
B25LA45432
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install 2 new special steel cantilever columns and wood shear wall
Permit Issued
Issued on 2/18/2026
Issuing Office
Current Status
Issued on 2/18/2026

Permit Application Status History

Submitted 10/28/2025 APPLICANT
Assigned to Plan Check Engineer 10/30/2025 HANS SANTIAGO
Corrections Issued 11/3/2025 HANS SANTIAGO
Quality Review Completed 11/5/2025 DANIEL CHAN
Applicant returned to address corrections 11/23/2025 HANS SANTIAGO
Applicant returned to address corrections 12/3/2025 HANS SANTIAGO
Plan Check Approved 12/3/2025 ANDREW SANTIAGO
Issued 2/18/2026 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 2/11/2026 KORNEL LELEA

Contact Information

Contractor Shaolian Sol K And Assoc Inc; Lic. No.: 720390-B       ,
Contractor Sks Construction; Lic. No.: 720390-B       ,
Engineer Labib,, Youhanna T.; Lic. No.: NA4549       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2026 Not Ready for Inspection FARHAD DADBIN
Pre-Inspection 5/18/2026 Approved FARHAD DADBIN
Deputy Drilled-In Anchors 6/3/2026 Conditional Approval FARHAD DADBIN
Footing/Foundation/Slab 6/10/2026 Approved FARHAD DADBIN
Deputy Reinf. Concrete 6/11/2026 Approved FARHAD DADBIN
Deputy Drilled-In Anchors 6/15/2026 Conditional Approval FARHAD DADBIN
Deputy Wood Construction 6/26/2026 Conditional Approval FARHAD DADBIN
Footing/Foundation/Slab 6/30/2026 Not Ready for Inspection FARHAD DADBIN
Wood Frame 7/10/2026 Not Ready for Inspection FARHAD DADBIN
Reinforced Concrete Frame 7/13/2026 Partial Approval FARHAD DADBIN
Wood Frame 7/14/2026 No Access for Inspection DANIEL VARNUM