1109 S CENTRAL AVE 90021

Certificate Information: 1109 S CENTRAL AVE 90021

Application / Permit
25016-10000-32226
Plan Check / Job No.
B25LA45429
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(8) Tire Shop
Work Description
Ch1A - CHANGE OF USE OF THE EXISTING POOL HOUSE USE BUILDING TO AUTOMATIVE TIRE/WHEEL REPAIR SHOP.
Permit Issued
Issued on 3/20/2026
Issuing Office
Current Status
Issued on 3/20/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/28/2025 APPLICANT
Assigned to Zoning Architect 11/6/2025 JASON BRAVO
Assigned to Plan Check Engineer 11/13/2025 MICHAEL LOPEZ
Corrections Issued 11/20/2025 MICHAEL LOPEZ
Quality Review Completed 11/24/2025 KEN GILL
Building Plans Picked Up 11/26/2025 APPLICANT
Disabled Access Plans Picked Up 12/10/2025 APPLICANT
Plan Check Approved 2/10/2026 MICHAEL LOPEZ
Issued 3/20/2026 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 12/13/2025 JEREMY CHOK
DAS Clearance Cleared 1/6/2026 MICHAEL LOPEZ
Zoning Plan Check Cleared 1/13/2026 MICHAEL LOPEZ
Eng Process Fee Ord 176,300 Cleared 1/15/2026 JESUS CISNEROS

Contact Information

Architect Zahabian,, Philip; Lic. No.: C23813 5237 NEWCASTLE AVE #307      ENCINO, CA 91316
Contractor Owner-Builder       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 5/21/2026 Partial Approval PAUL BAZERKANIAN
Wood Frame 5/21/2026 Approved PAUL BAZERKANIAN