2104 W 94TH PL 90047
Certificate Information: 2104 W 94TH PL 90047
- Application / Permit
- 25016-10000-32057
- Plan Check / Job No.
- B25LA45187
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED 20' X 20' GARAGE INTO A.D.U. PER GC & 66323(a)(2).
- Permit Issued
- Issued on 5/4/2026
- Issuing Office
- Current Status
- Issued on 5/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2025 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/31/2025 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 11/10/2025 | APPLICANT |
| Plan Check Approved | 5/4/2026 | SERGIO GUTIERREZ |
| Issued | 5/4/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/24/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 11/24/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 12/22/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/5/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 5/6/2026 | Conditional Approval | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/6/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 5/7/2026 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/7/2026 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 5/15/2026 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 5/15/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/15/2026 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/20/2026 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 5/20/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/20/2026 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/22/2026 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 5/22/2026 | Approved | RAUL BARAJAS |
| Green Building Rough | 5/22/2026 | Approved | RAUL BARAJAS |
| METHANE-Rough | 5/22/2026 | Approved | RAUL BARAJAS |
| Insulation | 5/27/2026 | Approved | ALEX COLIN |
| Drywall Nailing | 5/29/2026 | Approved | ALEX COLIN |
| Shower Pan | 6/2/2026 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 6/4/2026 | Approved | ALEX COLIN |