158 E 85TH ST 90003

Certificate Information: 158 E 85TH ST 90003

Application / Permit
25016-10000-32049
Plan Check / Job No.
B25LA45165
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL. EXISTING ROOM TO BE CONVERTED INTO A BEDROOM. REPLACE WINDOWS SAME SIZE/TYPE. NEW STUCCO.
Permit Issued
Issued on 4/7/2026
Issuing Office
Metro
Current Status
Permit Finaled on 4/27/2026

Permit Application Status History

Submitted 10/27/2025 APPLICANT
Assigned to Plan Check Engineer 10/30/2025 LUKE GONZALES
Corrections Issued 11/1/2025 LUKE GONZALES
Building Plans Picked Up 11/10/2025 APPLICANT
Plan Check Approved 4/3/2026 SERGIO GUTIERREZ
Issued 4/7/2026 APPLICANT
Permit Finaled 4/23/2026 JOHN QUINTANILLA

Permit Application Clearance Information

Historic Resource Verification Cleared 1/22/2026 YASMINE BASHIRI
"Q" conditions Cleared 2/10/2026 ANGELA WILLIAMS
Redevelopment Project Area Cleared 3/31/2026 YASMINE BASHIRI
Tenant Habitability Plan Cleared 4/1/2026 KORNEL LELEA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/9/2026 Corrections Issued GEM DE OCAMPO
ELECTRICAL-Rough 4/14/2026 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 4/14/2026 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 4/16/2026 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 4/16/2026 Approved JOHN QUINTANILLA
PLUMBING-Rough 4/16/2026 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 4/17/2026 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 4/21/2026 Approved JOHN QUINTANILLA
Final 4/23/2026 Permit Finaled JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/23/2026 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 4/23/2026 Approved JOHN QUINTANILLA