10868 W WILLOW CREST PL 91604

Certificate Information: 10868 W WILLOW CREST PL 91604

Application / Permit
25016-10000-31763
Plan Check / Job No.
B25LA44762
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: interior and exterior remodel to (e) SFD including, creating a new bedroom, bathroom, replacing all windows, new kitchen locations and layout, and relocate patio doors. No change in area.
Permit Issued
Issued on 12/15/2025
Issuing Office
Current Status
Issued on 12/15/2025

Permit Application Status History

Submitted 11/10/2025 APPLICANT
Assigned to Plan Check Engineer 11/13/2025 HOOMAN HAJIZADEH
Corrections Issued 11/13/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 11/25/2025 DAVID CASTILLO
Applicant returned to address corrections 11/26/2025 NAREG ATARIAN
Applicant returned to address corrections 12/4/2025 DAVID CASTILLO
Applicant returned to address corrections 12/11/2025 HOOMAN HAJIZADEH
Plan Check Approved 12/15/2025 KAVIAN REFAHI
Issued 12/15/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/24/2025 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 11/25/2025 BIAINA HARITUNIAN
Sewer availability Cleared 11/25/2025 BIAINA HARITUNIAN
Specific Plan Cleared 12/10/2025 RUBEN VASQUEZ

Contact Information

Architect Bdaiwi,, Mustafa; Lic. No.: C33953 30 CORPORATE PARK #102      IRVINE, CA 92606
Architect Bdaiwi,, Mustafa; Lic. No.: NA33953       ,
Contractor Owner-Builder       ,

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/30/2025 Conditional Approval ROY SPAULDING
Deputy Other (see comments) 12/30/2025 Conditional Approval ROY SPAULDING
Footing/Foundation/Slab 12/30/2025 Approved ROY SPAULDING
Excavation/Setback/Form/Re-Bar 12/31/2025 Approved ROY SPAULDING
Footing/Foundation/Slab 12/31/2025 Approved ROY SPAULDING
ELECTRICAL-Rough 2/19/2026 Approved ROY SPAULDING
HVAC-Rough 2/19/2026 Approved ROY SPAULDING
PLUMBING-Rough 2/19/2026 Approved ROY SPAULDING
BUILDING-Rough-Frame 2/27/2026 Corrections Issued BRIAN SULLIVAN
Interior/Exterior Lathing 2/27/2026 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 3/6/2026 Approved BRIAN SULLIVAN
Insulation 3/6/2026 Approved BRIAN SULLIVAN
Drywall Nailing 3/31/2026 Approved BRIAN SULLIVAN
Shower Pan 5/1/2026 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 5/7/2026 Approved ROY SPAULDING