17340 W HAMLIN ST 91406
Certificate Information: 17340 W HAMLIN ST 91406
- Application / Permit
- 25016-10000-30988
- Plan Check / Job No.
- B25LA43660
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF SFD
- Permit Issued
- Issued on 10/31/2025
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/28/2026
Permit Application Status History
| Submitted | 10/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 10/21/2025 | NEHEMIAS RAMOS |
| Building Plans Picked Up | 10/24/2025 | APPLICANT |
| Plan Check Approved | 10/29/2025 | YILE TIAN |
| Issued | 10/31/2025 | APPLICANT |
| Permit Finaled | 4/28/2026 | MORRIS JACKSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/12/2025 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Rough | 11/12/2025 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 11/12/2025 | Corrections Issued | MORRIS JACKSON |
| Gas Test | 11/12/2025 | Corrections Issued | MORRIS JACKSON |
| PLUMBING-Rough | 11/12/2025 | Corrections Issued | MORRIS JACKSON |
| Shower Pan | 11/12/2025 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 11/14/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Footing/Foundation/Slab | 11/14/2025 | Partial Approval | MORRIS JACKSON |
| Gas Test | 11/14/2025 | Approved | MORRIS JACKSON |
| HVAC-Rough | 11/14/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 11/14/2025 | Approved | MORRIS JACKSON |
| Shower Pan | 11/14/2025 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 11/19/2025 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Final | 11/19/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/19/2025 | Partial Approval | MORRIS JACKSON |
| Wood Frame | 11/19/2025 | Partial Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 11/25/2025 | Approved | MORRIS JACKSON |
| Insulation | 11/25/2025 | Approved | MORRIS JACKSON |
| Drywall Nailing | 12/2/2025 | Approved | JON MCHUGH |
| Final | 4/28/2026 | Permit Finaled | MORRIS JACKSON |
| Smoke Detectors | 4/28/2026 | Approved | MORRIS JACKSON |