14374 W LANARK ST 91402

Certificate Information: 14374 W LANARK ST 91402

Application / Permit
25016-10000-30889
Plan Check / Job No.
B25LA43520
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE TO DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE COMPLY WITH DEPARTMENT ORDER effective date 05/25/2012. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 11/20/2025
Issuing Office
Current Status
Issued on 11/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/16/2025 APPLICANT
Assigned to Plan Check Engineer 10/21/2025 CARLOS MONTES
Corrections Issued 10/21/2025 CARLOS MONTES
Building Plans Picked Up 10/23/2025 APPLICANT
Plan Check Approved 11/20/2025 CARLOS MONTES
Issued 11/20/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/6/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/6/2025 BIAINA HARITUNIAN
Sewer availability Cleared 11/6/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 11/20/2025 AARON DIZON

Contact Information

Contractor Silver Stone Remodeling Inc; Lic. No.: 1067851-B 27001 AGOURA ROAD SUITE 110      CALABASAS, CA 91301
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/4/2025 Approved MICKEY YAMASHITA
Footing/Foundation/Slab 12/4/2025 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 1/26/2026 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 1/26/2026 Approved MICKEY YAMASHITA
Green Building Rough 1/26/2026 Corrections Issued MICKEY YAMASHITA
HVAC-Rough 1/26/2026 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 1/26/2026 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 2/5/2026 Corrections Issued MICKEY YAMASHITA
HVAC-Rough 2/5/2026 Not Ready for Inspection MICKEY YAMASHITA
PLUMBING-Rough 2/5/2026 Corrections Issued MICKEY YAMASHITA
BUILDING-Rough-Frame 2/23/2026 Conditional Approval MICKEY YAMASHITA
ELECTRICAL-Rough 2/23/2026 Approved MICKEY YAMASHITA
Green Building Rough 2/23/2026 Corrections Issued MICKEY YAMASHITA
HVAC-Rough 2/23/2026 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 2/23/2026 Approved MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Partial Approval MICKEY YAMASHITA
HVAC-Rough 3/5/2026 Corrections Issued MICKEY YAMASHITA
Insulation 3/5/2026 Approved MICKEY YAMASHITA
Interior/Exterior Lathing 3/5/2026 Corrections Issued MICKEY YAMASHITA
Shower Pan 3/5/2026 Corrections Issued MICKEY YAMASHITA
BUILDING-Rough-Frame 3/9/2026 Conditional Approval MICKEY YAMASHITA
Green Building Rough 3/9/2026 Approved MICKEY YAMASHITA
HVAC-Rough 3/9/2026 Corrections Issued MICKEY YAMASHITA
Shower Pan 3/9/2026 Conditional Approval MICKEY YAMASHITA
BUILDING-Rough-Frame 3/17/2026 Approved MICKEY YAMASHITA
Drywall Nailing 3/17/2026 Approved MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 3/17/2026 Approved MICKEY YAMASHITA
HVAC-Rough 3/17/2026 Approved MICKEY YAMASHITA
Interior/Exterior Lathing 3/17/2026 Approved MICKEY YAMASHITA
Shower Pan 3/17/2026 Approved MICKEY YAMASHITA
Final 5/6/2026 No Access for Inspection MICKEY YAMASHITA
Green Building Final 5/6/2026 No Access for Inspection MICKEY YAMASHITA
HVAC-Final 5/6/2026 No Access for Inspection MICKEY YAMASHITA
PLUMBING-Final 5/6/2026 No Access for Inspection MICKEY YAMASHITA
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Not Ready MICKEY YAMASHITA
Smoke Detectors 5/6/2026 No Access for Inspection MICKEY YAMASHITA
ELECTRICAL-Final 5/21/2026 Approved JOEL GUARDADO
HVAC-Final 5/21/2026 Approved JOEL GUARDADO
MERV13>=Final 5/21/2026 Approved JOEL GUARDADO
PLUMBING-Final 5/21/2026 Approved JOEL GUARDADO