6200 S EILEEN AVE 90043
Certificate Information: 6200 S EILEEN AVE 90043
- Application / Permit
- 25016-10000-30485
- Plan Check / Job No.
- B25LA42841
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 11/3/2025
- Issuing Office
- Current Status
- Permit Finaled on 2/11/2026
Permit Application Status History
| Submitted | 10/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2025 | DANIEL YIP |
| Corrections Issued | 10/18/2025 | DANIEL YIP |
| Plan Check Approved | 11/2/2025 | DANIEL YIP |
| Issued | 11/3/2025 | APPLICANT |
| Permit Finaled | 2/10/2026 | MICHAEL LEWIS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/30/2025 | GERMAN RODRIGUEZ MENDO |
Contact Information
| Contractor | I M D Home Design Inc; Lic. No.: 1042619-B | , |
| Contractor | Imd Home Design Inc; Lic. No.: 1042619-B | , |
| Engineer | Mixter,, Thomas J; Lic. No.: NA51041 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2025 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 11/24/2025 | Approved | SABAS ALONSO |
| Deputy Drilled-In Anchors | 11/25/2025 | Conditional Approval | ANTHONY RAMOS |
| ELECTRICAL-Rough | 12/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 12/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 12/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 12/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 12/16/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 12/16/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 12/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 12/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 12/22/2025 | Approved | ANTHONY RAMOS |
| Gas Test | 12/22/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 12/22/2025 | Approved | ANTHONY RAMOS |
| PLUMBING-Rough | 12/22/2025 | Approved | ANTHONY RAMOS |
| Insulation | 12/24/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 12/30/2025 | Approved | DEVON JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2026 | Partial Inspection | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/13/2026 | Partial Inspection | MICHAEL LEWIS |
| Final | 2/10/2026 | Permit Finaled | MICHAEL LEWIS |