5907 W FOOTHILL DR 90068
Certificate Information: 5907 W FOOTHILL DR 90068
- Application / Permit
- 25016-10000-30361
- Plan Check / Job No.
- B25LA42650
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED RUMPUS ROOM TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1). EXISTING GARAGE TO REMAIN. "COMPLY WITH DEPARTMENT ORDER effective date 12/09/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 1/7/2026
- Issuing Office
- Current Status
- Issued on 1/7/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2025 | OMAR GARNICA |
| Corrections Issued | 10/24/2025 | OMAR GARNICA |
| Applicant returned to address corrections | 12/29/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 12/30/2025 | GIOVANNY CHAVEZ |
| Issued | 1/7/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/21/2025 | SAUL GARCIA |
| Sewer availability | Cleared | 12/21/2025 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2025 | SAUL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN FRANCHINI, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/20/2026 | Approved | PTOLEMY HILL |
| Final | 5/7/2026 | Not Ready for Inspection | JOEL ORDAZ |
| Green Building Final | 5/7/2026 | Not Ready for Inspection | JOEL ORDAZ |
| SGSOV-Seismic Gas S/O Valve | 5/7/2026 | SGSOV Not Ready | JOEL ORDAZ |
| Smoke Detectors | 5/7/2026 | Not Ready for Inspection | JOEL ORDAZ |
| Footing/Foundation/Slab | 6/3/2026 | Approved | JOEL ORDAZ |